Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
19
matching recommendationsSIC | 2821 | Plastics Materials And Resins |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0718 # 02 Y:2016 | 02 | 2016 | OPTIMIZE PLANT POWER FACTOR | $53,431 | $280,072 | Not Implemented |
AM0718 # 03 Y:2016 | 03 | 2016 | USE STEAM PRESSURE REDUCTION TO GENERATE POWER | $65,900 | $400,000 | Not Implemented |
AM0718 # 04 Y:2016 | 04 | 2016 | USE SYNTHETIC LUBRICANT | $28,832 | $0 | Implemented |
AM0718 # 05 Y:2016 | 05 | 2016 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $10,555 | $1,800 | Not Implemented |
AM0718 # 01 Y:2016 | 01 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $123,800 | $195,000 | Not Implemented |
WV0535 # 10 Y:2016 | 10 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $260 | $138 | Implemented |
WV0535 # 09 Y:2016 | 09 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $320 | $298 | Implemented |
WV0535 # 08 Y:2016 | 08 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $691 | $30 | Implemented |
WV0535 # 07 Y:2016 | 07 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,622 | $2,120 | Implemented |
WV0535 # 06 Y:2016 | 06 | 2016 | DEVELOP A REPAIR/REPLACE POLICY | $1,538 | $578 | Implemented |
WV0535 # 05 Y:2016 | 05 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,030 | $6,200 | Not Implemented |
WV0535 # 04 Y:2016 | 04 | 2016 | UPGRADE CONTROLS ON COMPRESSORS | $2,918 | $4,500 | Not Implemented |
WV0535 # 03 Y:2016 | 03 | 2016 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $3,206 | $1,000 | Implemented |
WV0535 # 02 Y:2016 | 02 | 2016 | INSULATE BARE EQUIPMENT | $4,153 | $511 | Implemented |
WV0535 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,812 | $8,931 | Not Implemented |
DL0159 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,590 | $188,100 | Implemented |
DL0159 # 03 Y:2016 | 03 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,300 | $17,825 | Implemented |
DL0159 # 02 Y:2016 | 02 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $48,000 | $100,750 | Implemented |
DL0159 # 01 Y:2016 | 01 | 2016 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $287,810 | $31,000 | Implemented |