Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

21

matching recommendations
Reset
SIC 2851 Paints And Allied Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
MA0820 # 05 Y:2020 05 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $204 $200 Implemented
MA0820 # 04 Y:2020 04 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $723 $300 Implemented
MA0820 # 03 Y:2020 03 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,673 $7,900 Not Implemented
MA0820 # 02 Y:2020 02 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,862 $11,220 Not Implemented
MA0820 # 01 Y:2020 01 2020 USE SOLAR HEAT TO MAKE ELECTRICTY $30,760 $129,192 Not Implemented
MA0633 # 04 Y:2008 04 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $2,171 $0 Not Implemented
MA0633 # 03 Y:2008 03 2008 INSTALL / REPAIR INSULATION ON STEAM LINES $857 $300 Not Implemented
MA0633 # 02 Y:2008 02 2008 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $8,944 $25,000 Not Implemented
MA0633 # 01 Y:2008 01 2008 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL $76,628 $85,000 Not Implemented
MA0573 # 03 Y:2005 03 2005 OPTIMIZE PLANT POWER FACTOR $5,270 $5,200 Not Implemented
MA0573 # 04 Y:2005 04 2005 INSULATE BARE EQUIPMENT $2,868 $3,920 Implemented
MA0573 # 02 Y:2005 02 2005 REPLACE BOILER $5,500 $15,900 Not Implemented
MA0573 # 01 Y:2005 01 2005 INSTALL TIMERS AND/OR THERMOSTATS $15,507 $6,435 Implemented
MA0481 # 01 Y:2001 01 2001 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $17,820 $30,000 Implemented
MA0481 # 08 Y:2001 08 2001 INSULATE FEEDWATER TANK $260 $1,300 Not Implemented
MA0481 # 07 Y:2001 07 2001 INSULATE FEEDWATER TANK $375 $1,000 Implemented
MA0481 # 06 Y:2001 06 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,400 $10,000 Not Implemented
MA0481 # 05 Y:2001 05 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $910 $1,315 Implemented
MA0481 # 04 Y:2001 04 2001 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,370 $7,000 Implemented
MA0481 # 03 Y:2001 03 2001 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $6,380 $4,800 Not Implemented
MA0481 # 02 Y:2001 02 2001 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $10,390 $5,500 Implemented