Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
Reset
SIC 2851 Paints And Allied Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
WV0579 # 10 Y:2019 10 2019 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $346 $33 Implemented
WV0579 # 09 Y:2019 09 2019 ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM $589 $1,000 Implemented
WV0579 # 08 Y:2019 08 2019 COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER $889 $1,460 Not Implemented
WV0579 # 07 Y:2019 07 2019 UPGRADE CONTROLS ON COMPRESSORS $1,120 $5,000 Not Implemented
WV0579 # 06 Y:2019 06 2019 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,976 $11,825 Not Implemented
WV0579 # 05 Y:2019 05 2019 DEVELOP A REPAIR/REPLACE POLICY $4,488 $879 Implemented
WV0579 # 04 Y:2019 04 2019 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $8,774 $22,038 Not Implemented
WV0579 # 03 Y:2019 03 2019 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES $14,452 $10,325 Not Implemented
WV0579 # 02 Y:2019 02 2019 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $18,379 $3,500 Implemented
WV0579 # 01 Y:2019 01 2019 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $95,486 $76,000 Not Implemented
WM0130 # 12 Y:2019 12 2019 USE PHOTOCELL CONTROLS $175 $404 Not Implemented
WM0130 # 13 Y:2019 13 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $154 $255 Not Implemented
WM0130 # 01 Y:2019 01 2019 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $18,300 $26,000 Not Implemented
WM0130 # 11 Y:2019 11 2019 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $597 $1,513 Not Implemented
WM0130 # 10 Y:2019 10 2019 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $698 $1,050 Not Implemented
WM0130 # 09 Y:2019 09 2019 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC $705 $315 Not Implemented
WM0130 # 08 Y:2019 08 2019 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,212 $800 Not Implemented
WM0130 # 07 Y:2019 07 2019 USE SYNTHETIC LUBRICANT $1,417 $497 Not Implemented
WM0130 # 06 Y:2019 06 2019 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,815 $4,154 Not Implemented
WM0130 # 05 Y:2019 05 2019 OPTIMIZE PLANT POWER FACTOR $2,616 $3,000 Not Implemented
WM0130 # 04 Y:2019 04 2019 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $5,515 $690 Not Implemented
WM0130 # 03 Y:2019 03 2019 USE SOLAR HEAT TO MAKE ELECTRICTY $13,760 $48,500 Not Implemented
WM0130 # 02 Y:2019 02 2019 REPAIR OR REPLACE STEAM TRAPS $15,350 $11,500 Not Implemented