Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
135
matching recommendationsSIC | 2865 | Cyclic Crudes And Intermediates |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0092 # 03 Y:2012 | 03 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $12,700 | $28,000 | Not Implemented |
DL0092 # 02 Y:2012 | 02 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $11,100 | $25,000 | Not Implemented |
DL0092 # 01 Y:2012 | 01 | 2012 | REPAIR AND ELIMINATE STEAM LEAKS | $50,827 | $48,000 | Not Implemented |
WV0450 # 11 Y:2012 | 11 | 2012 | DEVELOP A REPAIR/REPLACE POLICY | $8,489 | $1,210 | Implemented |
WV0450 # 05 Y:2012 | 05 | 2012 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $97,121 | $400,000 | Not Implemented |
WV0450 # 06 Y:2012 | 06 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $36,667 | $21,800 | Not Implemented |
WV0450 # 07 Y:2012 | 07 | 2012 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $11,389 | $6,500 | Implemented |
WV0450 # 13 Y:2012 | 13 | 2012 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,764 | $1,800 | Not Implemented |
WV0450 # 01 Y:2012 | 01 | 2012 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $173,557 | $1,000 | Implemented |
WV0450 # 03 Y:2012 | 03 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $130,899 | $157,320 | Implemented |
WV0450 # 02 Y:2012 | 02 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $141,590 | $210,000 | Not Implemented |
WV0450 # 04 Y:2012 | 04 | 2012 | REDESIGN PROCESS | $102,043 | $230,000 | Not Implemented |
WV0450 # 09 Y:2012 | 09 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $9,686 | $21,120 | Not Implemented |
WV0450 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,953 | $18,267 | Implemented |
WV0450 # 12 Y:2012 | 12 | 2012 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $7,314 | $3,360 | Not Implemented |
WV0450 # 08 Y:2012 | 08 | 2012 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $10,199 | $1,000 | Not Implemented |
DL0076 # 04 Y:2011 | 04 | 2011 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $42,900 | $380,000 | Not Implemented |
DL0076 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,500 | $4,000 | Implemented |
DL0076 # 02 Y:2011 | 02 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,650 | $24,000 | Not Implemented |
DL0076 # 01 Y:2011 | 01 | 2011 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $63,000 | $100 | Implemented |
UM0306 # 04 Y:2006 | 04 | 2006 | ELIMINATE COOLING OF PROCESS STREAMS WHICH SUBSEQUENTLY MUST BE HEATED AND VICE VERSA | $8,336 | $7,520 | Implemented |
UM0306 # 06 Y:2006 | 06 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,482 | $2,429 | Not Implemented |
UM0306 # 07 Y:2006 | 07 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,558 | $197 | Implemented |
UM0306 # 01 Y:2006 | 01 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,385 | $2,500 | Implemented |
UM0306 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $11,812 | $22,458 | Not Implemented |