Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,603
matching recommendationsSIC | 289 | Miscellaneous Chemical Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0226 # 04 Y:1998 | 04 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $251 | $75 | Implemented |
AS0226 # 05 Y:1998 | 05 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,554 | $60 | Implemented |
AS0226 # 06 Y:1998 | 06 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $342 | $212 | Not Implemented |
AS0226 # 07 Y:1998 | 07 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,126 | $620 | Implemented |
AS0226 # 08 Y:1998 | 08 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,203 | $30 | Implemented |
AS0226 # 09 Y:1998 | 09 | 1998 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $1,827 | $625 | Implemented |
AS0226 # 10 Y:1998 | 10 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $760 | $60 | Implemented |
MO0229 # 01 Y:1998 | 01 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $3,111,888 | $0 | Not Implemented |
MO0229 # 02 Y:1998 | 02 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $11,035 | $3,700 | Not Implemented |
MO0229 # 03 Y:1998 | 03 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,548 | $7,376 | Implemented |
MO0229 # 04 Y:1998 | 04 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $708 | $1,568 | Implemented |
MO0229 # 05 Y:1998 | 05 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,899 | $40 | Implemented |
MO0229 # 06 Y:1998 | 06 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,496 | $52 | Not Implemented |
MO0229 # 07 Y:1998 | 07 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,484 | $6,161 | Implemented |
MO0229 # 08 Y:1998 | 08 | 1998 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $720 | $2,080 | Not Implemented |
GT0634 # 01 Y:1998 | 01 | 1998 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $290 | $800 | Not Implemented |
GT0634 # 02 Y:1998 | 02 | 1998 | INSULATE BARE EQUIPMENT | $1,600 | $840 | Not Implemented |
GT0634 # 03 Y:1998 | 03 | 1998 | REDUCE VENTILATION AIR | $1,900 | $2,000 | Not Implemented |
GT0634 # 04 Y:1998 | 04 | 1998 | COVER OPEN TANKS | $80 | $300 | Implemented |
GT0634 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $932 | $3,180 | Implemented |
GT0634 # 06 Y:1998 | 06 | 1998 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $1,220 | $0 | Implemented |
GT0634 # 07 Y:1998 | 07 | 1998 | PURCHASE MATERIAL FROM SUPPLIER IN CUSTOMIZED PACKAGING | $2,730 | $780 | Not Implemented |
DS0106 # 01 Y:1998 | 01 | 1998 | INSULATE BARE EQUIPMENT | $3,231 | $2,430 | Implemented |
DS0106 # 02 Y:1998 | 02 | 1998 | REPAIR AND ELIMINATE STEAM LEAKS | $1,009 | $400 | Implemented |
DS0106 # 03 Y:1998 | 03 | 1998 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $15,659 | $199 | Not Implemented |