Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 29 | Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IC0062 # 06 Y:2003 | 06 | 2003 | INSTALL / REPAIR INSULATION ON STEAM LINES | $20,526 | $21,542 | Implemented |
IC0062 # 05 Y:2003 | 05 | 2003 | REPAIR AND ELIMINATE STEAM LEAKS | $45,681 | $10,200 | Implemented |
IC0062 # 04 Y:2003 | 04 | 2003 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $8,560 | $5,280 | Implemented |
IC0062 # 03 Y:2003 | 03 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,105 | $0 | Implemented |
IC0062 # 02 Y:2003 | 02 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,779 | $14,546 | Implemented |
IC0062 # 01 Y:2003 | 01 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,452 | $6,197 | Not Implemented |
IC0061 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,505 | $31,380 | Not Implemented |
IC0061 # 03 Y:2003 | 03 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $20,440 | $26,755 | Not Implemented |
IC0061 # 02 Y:2003 | 02 | 2003 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $3,861 | $2,640 | Implemented |
IC0061 # 01 Y:2003 | 01 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $694 | $1,859 | Implemented |
WI0243 # 02 Y:1995 | 02 | 1995 | INSTALL TIMERS AND/OR THERMOSTATS | $6,975 | $400 | Implemented |
WI0243 # 10 Y:1995 | 10 | 1995 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $13,399 | $9,000 | Not Implemented |
WI0243 # 09 Y:1995 | 09 | 1995 | INSULATE BARE EQUIPMENT | $248 | $672 | Not Implemented |
WI0243 # 08 Y:1995 | 08 | 1995 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $445 | $700 | Not Implemented |
WI0243 # 07 Y:1995 | 07 | 1995 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $898 | $1,796 | Implemented |
WI0243 # 06 Y:1995 | 06 | 1995 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,126 | $538 | Not Implemented |
WI0243 # 05 Y:1995 | 05 | 1995 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,773 | $1,500 | Implemented |
WI0243 # 04 Y:1995 | 04 | 1995 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,111 | $6,000 | Not Implemented |
WI0243 # 03 Y:1995 | 03 | 1995 | REPLACE BOILER | $3,712 | $12,000 | Not Implemented |
WI0243 # 01 Y:1995 | 01 | 1995 | DIRECT WARMEST AIR TO COMBUSTION INTAKE | $4,132 | $10,000 | Not Implemented |
WI0192 # 01 Y:1993 | 01 | 1993 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,147 | $500 | Implemented |
WI0192 # 02 Y:1993 | 02 | 1993 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $484 | $1,000 | Not Implemented |
WI0192 # 03 Y:1993 | 03 | 1993 | INSULATE BARE EQUIPMENT | $525 | $314 | Not Implemented |
WI0192 # 04 Y:1993 | 04 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,334 | $3,400 | Implemented |
WI0192 # 05 Y:1993 | 05 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $498 | $1,063 | Implemented |