Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
32
matching recommendationsSIC | 295 | Asphalt Paving And Roofing Materials |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0619 # 01 Y:1997 | 01 | 1997 | RECOVER WASTE HEAT FROM EQUIPMENT | $66,400 | $60,620 | Not Implemented |
GT0619 # 02 Y:1997 | 02 | 1997 | INCREASE AMOUNT OF CONDENSATE RETURNED | $62,700 | $18,000 | Implemented |
GT0619 # 03 Y:1997 | 03 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $990 | $500 | Implemented |
GT0619 # 04 Y:1997 | 04 | 1997 | INSULATE BARE EQUIPMENT | $116 | $310 | Implemented |
GT0619 # 05 Y:1997 | 05 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,050 | $700 | Not Implemented |
GT0619 # 06 Y:1997 | 06 | 1997 | USE RE-USABLE FILTERS | $60,000 | $8,000 | Not Implemented |
SF0118 # 09 Y:1997 | 09 | 1997 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $499 | $250 | Implemented |
SF0118 # 05 Y:1997 | 05 | 1997 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $31,007 | $140,000 | Not Implemented |
SF0118 # 04 Y:1997 | 04 | 1997 | OPTIMIZE PLANT POWER FACTOR | $1,631 | $2,409 | Not Implemented |
SF0118 # 03 Y:1997 | 03 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,464 | $1,356 | Implemented |
SF0118 # 02 Y:1997 | 02 | 1997 | USE PHOTOCELL CONTROLS | $3,456 | $2,000 | Implemented |
SF0118 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,575 | $2,700 | Implemented |
SF0118 # 10 Y:1997 | 10 | 1997 | INSTALL REDUNDANT EQUIPMENT TO AVOID LOSSES CAUSED BY EQUIPMENT FAILURE AND ROUTINE MAINTENANCE | $4,583 | $500 | Implemented |
SF0118 # 11 Y:1997 | 11 | 1997 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $46,724 | $32,060 | Implemented |
SF0118 # 06 Y:1997 | 06 | 1997 | INSTALL / REPAIR INSULATION ON STEAM LINES | $369 | $365 | Implemented |
SF0118 # 07 Y:1997 | 07 | 1997 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,770 | $14,926 | Implemented |
SF0118 # 08 Y:1997 | 08 | 1997 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,598 | $14,138 | Implemented |
OR0294 # 05 Y:1997 | 05 | 1997 | OPTIMIZE PLANT POWER FACTOR | $861 | $2,600 | Not Implemented |
OR0294 # 04 Y:1997 | 04 | 1997 | UPGRADE CONTROLS ON COMPRESSORS | $1,540 | $3,700 | Not Implemented |
OR0294 # 03 Y:1997 | 03 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,520 | $1,000 | Not Implemented |
OR0294 # 08 Y:1997 | 08 | 1997 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $9,140 | $80,000 | Not Implemented |
OR0294 # 09 Y:1997 | 09 | 1997 | USE A DIFFERENT OR RECYCLED RAW MATERIAL | $117,450 | $206,000 | Not Implemented |
OR0294 # 10 Y:1997 | 10 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $11,700 | $22,500 | Not Implemented |
OR0294 # 11 Y:1997 | 11 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $2,160 | $0 | Implemented |
OR0294 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,320 | $500 | Implemented |