Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsSIC | 299 | Misc. Petroleum And Coal Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1081 # 06 Y:2023 | 06 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $13,097 | $11,114 | Implemented |
OK1081 # 05 Y:2023 | 05 | 2023 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $8,026 | $7,020 | Implemented |
OK1081 # 02 Y:2023 | 02 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $10,608 | $0 | Implemented |
OK1081 # 07 Y:2023 | 07 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,263 | $600 | Implemented |
KU0415 # 06 Y:1993 | 06 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $230 | $100 | Implemented |
KU0415 # 02 Y:1993 | 02 | 1993 | INSTALL / REPAIR INSULATION ON STEAM LINES | $983 | $2,255 | Implemented |
KU0415 # 01 Y:1993 | 01 | 1993 | REPAIR AND ELIMINATE STEAM LEAKS | $1,558 | $150 | Implemented |
KU0207 # 09 Y:1986 | 09 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,433 | $0 | Implemented |
KU0207 # 17 Y:1986 | 17 | 1986 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $160 | $300 | Implemented |
KU0207 # 16 Y:1986 | 16 | 1986 | INSTALL / REPAIR INSULATION ON STEAM LINES | $128 | $100 | Implemented |
KU0207 # 14 Y:1986 | 14 | 1986 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $454 | $20 | Implemented |
KU0207 # 13 Y:1986 | 13 | 1986 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $469 | $0 | Implemented |
KU0207 # 12 Y:1986 | 12 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $150 | Implemented |
KU0207 # 11 Y:1986 | 11 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Implemented |
KU0207 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,817 | $52 | Implemented |
KU0207 # 06 Y:1986 | 06 | 1986 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,637 | $6,030 | Implemented |
KU0207 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $9,165 | $1,494 | Implemented |
KU0207 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,480 | $0 | Implemented |
KU0207 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,525 | $0 | Implemented |
KU0104 # 01 Y:1983 | 01 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,312 | $1,500 | Implemented |
KU0104 # 07 Y:1983 | 07 | 1983 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $2,308 | $132 | Implemented |
KU0104 # 06 Y:1983 | 06 | 1983 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,791 | $5,000 | Implemented |
KU0104 # 05 Y:1983 | 05 | 1983 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $916 | $800 | Implemented |
KU0104 # 04 Y:1983 | 04 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $1,624 | $400 | Implemented |
KU0104 # 03 Y:1983 | 03 | 1983 | REPAIR OR REPLACE STEAM TRAPS | $2,673 | $2,000 | Implemented |