Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
274
matching recommendationsSIC | 2992 | Lubricating Oils And Greases |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0052 # 05 Y:1993 | 05 | 1993 | MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT | $9,280 | $2,450 | Implemented |
SD0052 # 06 Y:1993 | 06 | 1993 | REPAIR OR REPLACE STEAM TRAPS | $14,542 | $6,550 | Implemented |
SD0052 # 07 Y:1993 | 07 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,035 | $40 | Implemented |
SD0052 # 08 Y:1993 | 08 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $434 | $0 | Implemented |
SD0052 # 09 Y:1993 | 09 | 1993 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,893 | $3,900 | Not Implemented |
SD0052 # 10 Y:1993 | 10 | 1993 | INSTALL SET-BACK TIMERS | $903 | $1,240 | Not Implemented |
KU0316 # 01 Y:1990 | 01 | 1990 | INSTALL SET-BACK TIMERS | $3,487 | $2,075 | Implemented |
KU0316 # 02 Y:1990 | 02 | 1990 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $924 | $1,005 | Implemented |
KU0316 # 03 Y:1990 | 03 | 1990 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $7,122 | $15,000 | Implemented |
KU0316 # 04 Y:1990 | 04 | 1990 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,990 | $7,200 | Not Implemented |
KU0316 # 05 Y:1990 | 05 | 1990 | OPTIMIZE PLANT POWER FACTOR | $2,160 | $2,250 | Implemented |
KU0316 # 06 Y:1990 | 06 | 1990 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,034 | $1,000 | Implemented |
KU0316 # 07 Y:1990 | 07 | 1990 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $117 | $0 | Not Implemented |
KU0207 # 01 Y:1986 | 01 | 1986 | BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT | $164,472 | $840,000 | Not Implemented |
KU0207 # 02 Y:1986 | 02 | 1986 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $18,525 | $0 | Implemented |
KU0207 # 03 Y:1986 | 03 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $9,480 | $0 | Implemented |
KU0207 # 04 Y:1986 | 04 | 1986 | INSTALL SET-BACK TIMERS | $9,165 | $1,494 | Implemented |
KU0207 # 05 Y:1986 | 05 | 1986 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $6,099 | $12,675 | Not Implemented |
KU0207 # 06 Y:1986 | 06 | 1986 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $5,637 | $6,030 | Implemented |
KU0207 # 07 Y:1986 | 07 | 1986 | INSTALL TIMERS AND/OR THERMOSTATS | $2,817 | $52 | Implemented |
KU0207 # 08 Y:1986 | 08 | 1986 | ADD AIR SHIELDS TO TRUCKS TO INCREASE FUEL MILEAGE | $1,802 | $0 | Not Implemented |
KU0207 # 09 Y:1986 | 09 | 1986 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,433 | $0 | Implemented |
KU0207 # 10 Y:1986 | 10 | 1986 | INSTALL STEAM TRAP | $600 | $90 | Not Implemented |
KU0207 # 11 Y:1986 | 11 | 1986 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $547 | $0 | Implemented |
KU0207 # 12 Y:1986 | 12 | 1986 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $516 | $150 | Implemented |