Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,816
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
DL0198 # 09 Y:2021 | 09 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $33,740 | $14,428 | Implemented |
WV0615 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,040 | $233 | Implemented |
WV0615 # 05 Y:2021 | 05 | 2021 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,781 | $2,300 | Implemented |
WV0615 # 06 Y:2021 | 06 | 2021 | DEVELOP A REPAIR/REPLACE POLICY | $2,598 | $5,175 | Implemented |
WV0615 # 07 Y:2021 | 07 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $944 | $70 | Implemented |
WV0615 # 08 Y:2021 | 08 | 2021 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $913 | $688 | Implemented |
WV0615 # 10 Y:2021 | 10 | 2021 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $307 | $1,000 | Implemented |
MI0396 # 01 Y:2021 | 01 | 2021 | PAY UTILITY BILLS ON TIME | $27,408 | $0 | Implemented |
MI0396 # 04 Y:2021 | 04 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,908 | $2,020 | Implemented |
AM0833 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $80,120 | $8,000 | Implemented |
AM0833 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,337 | $9,462 | Implemented |
AM0833 # 03 Y:2022 | 03 | 2022 | INSTALL OCCUPANCY SENSORS | $71 | $90 | Implemented |
AM0833 # 05 Y:2022 | 05 | 2022 | USE PHOTOCELL CONTROLS | $457 | $410 | Implemented |
AM0833 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,688 | $529 | Implemented |
AM0833 # 07 Y:2022 | 07 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $390 | $15 | Implemented |
AM0833 # 08 Y:2022 | 08 | 2022 | AVOID INTRODUCING HOT, HUMID, OR DIRTY AIR INTO HVAC SYSTEM | $1,873 | $930 | Implemented |
TT0262 # 04 Y:2021 | 04 | 2021 | INSULATE BARE EQUIPMENT | $4,646 | $3,879 | Implemented |
TT0262 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,023 | $2,762 | Implemented |
AM0832 # 01 Y:2022 | 01 | 2022 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $234,880 | $15,000 | Implemented |
AM0832 # 02 Y:2022 | 02 | 2022 | PAY UTILITY BILLS ON TIME | $725 | $0 | Implemented |
AM0832 # 04 Y:2022 | 04 | 2022 | USE SYNTHETIC LUBRICANT | $3,290 | $500 | Implemented |
AM0832 # 05 Y:2022 | 05 | 2022 | MAINTAIN MACHINES TO REDUCE LEAKS | $19,925 | $50,000 | Implemented |
IC0250 # 01 Y:2021 | 01 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,107 | $4,150 | Implemented |
IC0250 # 03 Y:2021 | 03 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,708 | $10,610 | Implemented |
IC0250 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $473 | $0 | Implemented |