Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
7,816
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0280 # 05 Y:1989 | 05 | 1989 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $250 | $0 | Implemented |
KU0280 # 07 Y:1989 | 07 | 1989 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $143 | $40 | Implemented |
RU0054 # 03 Y:1989 | 03 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,084 | $0 | Implemented |
RU0054 # 06 Y:1989 | 06 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,711 | $8,300 | Implemented |
WI0047 # 01 Y:1989 | 01 | 1989 | IMPROVE LUBRICATION PRACTICES | $3,210 | $500 | Implemented |
WI0047 # 02 Y:1989 | 02 | 1989 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $3,901 | $1,300 | Implemented |
WI0047 # 03 Y:1989 | 03 | 1989 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $238 | $0 | Implemented |
WI0047 # 05 Y:1989 | 05 | 1989 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,913 | $3,600 | Implemented |
WI0047 # 06 Y:1989 | 06 | 1989 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,766 | $2,100 | Implemented |
LT0142 # 02 Y:1989 | 02 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,542 | $442 | Implemented |
LT0142 # 03 Y:1989 | 03 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,008 | $442 | Implemented |
LT0142 # 04 Y:1989 | 04 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,470 | $400 | Implemented |
LT0142 # 05 Y:1989 | 05 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $3,092 | $200 | Implemented |
LT0142 # 07 Y:1989 | 07 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $423 | $100 | Implemented |
LT0142 # 08 Y:1989 | 08 | 1989 | REPAIR AND ELIMINATE STEAM LEAKS | $3,193 | $224 | Implemented |
MA0142 # 01 Y:1989 | 01 | 1989 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $16,859 | $570 | Implemented |
MA0142 # 06 Y:1989 | 06 | 1989 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $27,100 | $13,000 | Implemented |
MA0142 # 07 Y:1989 | 07 | 1989 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $52,700 | $680 | Implemented |
TN0357 # 01 Y:1989 | 01 | 1989 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,000 | $900 | Implemented |
TN0357 # 03 Y:1989 | 03 | 1989 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,409 | $1,380 | Implemented |
TN0357 # 04 Y:1989 | 04 | 1989 | INSULATE BARE EQUIPMENT | $3,004 | $355 | Implemented |
TN0357 # 05 Y:1989 | 05 | 1989 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $928 | $1,110 | Implemented |
TN0357 # 06 Y:1989 | 06 | 1989 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,541 | $0 | Implemented |
TN0357 # 07 Y:1989 | 07 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $1,315 | $560 | Implemented |
TN0357 # 09 Y:1989 | 09 | 1989 | DISCONNECT BALLASTS | $254 | $273 | Implemented |