Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,100
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
BD0492 # 10 Y:2016 | 10 | 2016 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $285 | $200 | n/a |
BD0492 # 11 Y:2016 | 11 | 2016 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $225 | $200 | n/a |
SU0427 # 01 Y:2016 | 01 | 2016 | INSTALL OCCUPANCY SENSORS | $442 | $317 | Implemented |
SU0427 # 02 Y:2016 | 02 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $195 | $173 | Not Implemented |
SU0427 # 03 Y:2016 | 03 | 2016 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $240 | $484 | Not Implemented |
SU0427 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,703 | $34,086 | Implemented |
SU0427 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $124 | $556 | Implemented |
SU0427 # 06 Y:2016 | 06 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $189 | $924 | Implemented |
UK1610 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,688 | $4,985 | Implemented |
UK1610 # 02 Y:2016 | 02 | 2016 | INSTALL OCCUPANCY SENSORS | $374 | $148 | Implemented |
UK1610 # 03 Y:2016 | 03 | 2016 | DISCONNECT BALLASTS | $92 | $34 | Not Implemented |
UK1610 # 04 Y:2016 | 04 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $240 | $470 | Not Implemented |
UK1610 # 05 Y:2016 | 05 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $525 | $0 | Implemented |
UK1610 # 06 Y:2016 | 06 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $490 | $0 | Not Implemented |
UK1610 # 07 Y:2016 | 07 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $196 | $500 | Implemented |
UK1610 # 08 Y:2016 | 08 | 2016 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $1,083 | $500 | Implemented |
UK1610 # 09 Y:2016 | 09 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $63 | $0 | Not Implemented |
MA0768 # 01 Y:2016 | 01 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,870 | $3,830 | Not Implemented |
MA0768 # 02 Y:2016 | 02 | 2016 | INSTALL / REPAIR INSULATION ON STEAM LINES | $939 | $3,914 | Implemented |
MA0768 # 03 Y:2016 | 03 | 2016 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $871 | $1,000 | Implemented |
MA0768 # 04 Y:2016 | 04 | 2016 | MINIMIZE WATER USAGE | $587 | $3,650 | Implemented |
MA0768 # 05 Y:2016 | 05 | 2016 | OPTIMIZE PLANT POWER FACTOR | $515 | $3,480 | Not Implemented |
MA0768 # 06 Y:2016 | 06 | 2016 | CLOSE OFF UNNEEDED STEAM LINES | $376 | $4,348 | Implemented |
MA0768 # 07 Y:2016 | 07 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $331 | $2,648 | Not Implemented |
MA0768 # 08 Y:2016 | 08 | 2016 | INSTALL / REPAIR INSULATION ON STEAM LINES | $313 | $1,944 | Implemented |