Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
557
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0296 # 02 Y:2010 | 02 | 2010 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,760 | $5,000 | Not Implemented |
LE0296 # 03 Y:2010 | 03 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,665 | $1,768 | Implemented |
LE0296 # 04 Y:2010 | 04 | 2010 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $1,340 | $5,200 | Not Implemented |
LE0296 # 05 Y:2010 | 05 | 2010 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $878 | $2,338 | Implemented |
LE0296 # 06 Y:2010 | 06 | 2010 | INSTALL OCCUPANCY SENSORS | $455 | $420 | Not Implemented |
LE0296 # 07 Y:2010 | 07 | 2010 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $418 | $182 | Implemented |
LE0296 # 08 Y:2010 | 08 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,738 | $17,123 | Not Implemented |
LE0287 # 01 Y:2009 | 01 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $184,606 | $250,000 | Not Implemented |
LE0287 # 02 Y:2009 | 02 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $220,823 | $50,000 | Not Implemented |
LE0287 # 03 Y:2009 | 03 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $79,515 | $8,000 | Not Implemented |
LE0287 # 04 Y:2009 | 04 | 2009 | INSTALL TIMERS AND/OR THERMOSTATS | $36,003 | $650 | Not Implemented |
LE0287 # 05 Y:2009 | 05 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $19,644 | $17,000 | Not Implemented |
LE0287 # 06 Y:2009 | 06 | 2009 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $13,621 | $7,167 | Not Implemented |
LE0287 # 07 Y:2009 | 07 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,058 | $1,840 | Implemented |
LE0287 # 08 Y:2009 | 08 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,998 | $27,281 | Not Implemented |
DL0011 # 01 Y:2008 | 01 | 2008 | TURN OFF EQUIPMENT WHEN NOT IN USE | $19,525 | $0 | Implemented |
DL0011 # 02 Y:2008 | 02 | 2008 | UPGRADE CONTROLS ON COMPRESSORS | $9,089 | $10,000 | Not Implemented |
DL0011 # 03 Y:2008 | 03 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,807 | $160 | Not Implemented |
DL0011 # 04 Y:2008 | 04 | 2008 | INSULATE BARE EQUIPMENT | $1,472 | $268 | Not Implemented |
DL0011 # 05 Y:2008 | 05 | 2008 | INSTALL OCCUPANCY SENSORS | $165 | $127 | Implemented |
DL0011 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,968 | $36,000 | Implemented |
DL0011 # 07 Y:2008 | 07 | 2008 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,226 | $1,600,000 | Not Implemented |
LE0264 # 01 Y:2007 | 01 | 2007 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $25,680 | $50,000 | Implemented |
LE0264 # 02 Y:2007 | 02 | 2007 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,103 | $2,500 | Implemented |
LE0264 # 03 Y:2007 | 03 | 2007 | INSTALL TIMERS AND/OR THERMOSTATS | $4,204 | $2,000 | Implemented |