Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,163
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0652 # 01 Y:2014 | 01 | 2014 | INSULATE BARE EQUIPMENT | $91,770 | $1,500 | Not Implemented |
AM0652 # 02 Y:2014 | 02 | 2014 | OPTIMIZE PLANT POWER FACTOR | $14,900 | $37,100 | Implemented |
AM0652 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,965 | $5,090 | Not Implemented |
AM0652 # 04 Y:2014 | 04 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,680 | $30,600 | Implemented |
AM0652 # 05 Y:2014 | 05 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,195 | $500 | Implemented |
AM0652 # 06 Y:2014 | 06 | 2014 | INSTALL SKYLIGHTS | $1,040 | $3,790 | Not Implemented |
AM0652 # 07 Y:2014 | 07 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $740 | $20 | Implemented |
AM0652 # 08 Y:2014 | 08 | 2014 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $320 | $0 | Implemented |
AM0652 # 09 Y:2014 | 09 | 2014 | USE PHOTOCELL CONTROLS | $150 | $0 | Implemented |
AM0639 # 04 Y:2013 | 04 | 2013 | CLEAN CONDENSER TUBES | $6,020 | $7,540 | Implemented |
AM0639 # 05 Y:2013 | 05 | 2013 | OPTIMIZE PLANT POWER FACTOR | $5,960 | $13,780 | Not Implemented |
AM0639 # 06 Y:2013 | 06 | 2013 | USE SYNTHETIC LUBRICANT | $4,190 | $0 | Implemented |
AM0639 # 07 Y:2013 | 07 | 2013 | INSTALL OCCUPANCY SENSORS | $1,440 | $1,840 | Not Implemented |
AM0639 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,680 | $500 | Implemented |
AM0639 # 02 Y:2013 | 02 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,550 | $18 | Implemented |
AM0639 # 03 Y:2013 | 03 | 2013 | PAY UTILITY BILLS ON TIME | $7,089 | $0 | Implemented |
OK0841 # 01 Y:2013 | 01 | 2013 | RECOVER WASTE HEAT FROM EQUIPMENT | $44,134 | $43,500 | Not Implemented |
OK0841 # 02 Y:2013 | 02 | 2013 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $68,923 | $4,000 | Not Implemented |
OK0841 # 03 Y:2013 | 03 | 2013 | INSULATE BARE EQUIPMENT | $15,201 | $4,500 | Not Implemented |
OK0841 # 04 Y:2013 | 04 | 2013 | INSTALL OCCUPANCY SENSORS | $693 | $4,051 | Implemented |
OK0841 # 05 Y:2013 | 05 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $151 | $228 | Not Implemented |
OK0841 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $40,107 | $74,800 | Not Implemented |
OK0841 # 07 Y:2013 | 07 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,217 | $4,000 | Implemented |
OK0841 # 08 Y:2013 | 08 | 2013 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,111 | $1,134 | Implemented |
OK0841 # 09 Y:2013 | 09 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $33,063 | $21,269 | Not Implemented |