Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,583

matching recommendations
Reset
SIC 30 Rubber And Miscellaneous Plastics Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SF0351 # 03 Y:2008 03 2008 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,240 $150 Not Implemented
SF0351 # 04 Y:2008 04 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,173 $0 Not Implemented
SF0351 # 05 Y:2008 05 2008 INSULATE BARE EQUIPMENT $584 $0 Not Implemented
SF0351 # 06 Y:2008 06 2008 INSTALL OCCUPANCY SENSORS $2,396 $290 Not Implemented
SF0351 # 07 Y:2008 07 2008 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,173 $228 Not Implemented
SF0351 # 08 Y:2008 08 2008 INSULATE BARE EQUIPMENT $685 $503 Not Implemented
SF0351 # 09 Y:2008 09 2008 REDUCE EXCESSIVE BOILER BLOWDOWN $1,877 $2,802 Not Implemented
SF0351 # 10 Y:2008 10 2008 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $1,144 $1,792 Not Implemented
SF0351 # 11 Y:2008 11 2008 INSULATE BARE EQUIPMENT $493 $979 Not Implemented
SF0351 # 12 Y:2008 12 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $23,836 $93,064 Implemented
SF0350 # 01 Y:2007 01 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,920 $300 Implemented
SF0350 # 02 Y:2007 02 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,274 $1,332 Implemented
SF0350 # 03 Y:2007 03 2007 INSTALL OCCUPANCY SENSORS $399 $492 Implemented
SF0350 # 04 Y:2007 04 2007 INSULATE BARE EQUIPMENT $1,126 $2,145 Not Implemented
SF0350 # 05 Y:2007 05 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $644 $4,267 Not Implemented
SF0350 # 06 Y:2007 06 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,467 $9,827 Not Implemented
SF0345 # 01 Y:2007 01 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $3,945 $711 Not Implemented
SF0345 # 02 Y:2007 02 2007 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,951 $2,939 Not Implemented
SF0345 # 03 Y:2007 03 2007 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $9,919 $5,140 Not Implemented
SF0345 # 04 Y:2007 04 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $1,019 $711 Not Implemented
SF0345 # 05 Y:2007 05 2007 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $4,266 $4,307 Not Implemented
SF0345 # 06 Y:2007 06 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,999 $3,759 Implemented
SF0345 # 07 Y:2007 07 2007 INSTALL OCCUPANCY SENSORS $511 $1,404 Not Implemented
SF0345 # 08 Y:2007 08 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,115 $6,510 Implemented
SF0345 # 09 Y:2007 09 2007 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,339 $4,380 Implemented