Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,096
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK1094 # 02 Y:2023 | 02 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $3,917 | $22,000 | Implemented |
OK1094 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $573 | $870 | Implemented |
OK1094 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,890 | $94,115 | Implemented |
OK1094 # 05 Y:2023 | 05 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $93,859 | $858,000 | Not Implemented |
OK1094 # 06 Y:2023 | 06 | 2023 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,239 | $12,700 | Not Implemented |
UF0597 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $20,876 | $14,705 | Implemented |
UF0597 # 02 Y:2023 | 02 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,736 | $15,722 | Implemented |
UF0597 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,612 | $25,370 | Implemented |
UF0597 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,142 | $22,000 | Implemented |
UF0597 # 05 Y:2023 | 05 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,959 | $11,134 | Implemented |
UF0597 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,382 | $13,706 | Implemented |
UF0597 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,699 | $4,994 | Implemented |
UF0597 # 08 Y:2023 | 08 | 2023 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $51,744 | $18,218 | Implemented |
UF0597 # 09 Y:2023 | 09 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $35,500 | $4,261 | Implemented |
KS2318 # 01 Y:2023 | 01 | 2023 | REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES | $14,419 | $320 | n/a |
KS2318 # 02 Y:2023 | 02 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,203 | $60 | n/a |
KS2318 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,814 | $28,960 | n/a |
KS2318 # 04 Y:2023 | 04 | 2023 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $2,238 | $1,864 | n/a |
KS2318 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $224 | $765 | n/a |
KS2318 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,448 | $8,951 | n/a |
KS2318 # 07 Y:2023 | 07 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $43,077 | $421,486 | n/a |
IC0282 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,637 | $3,994 | Implemented |
IC0282 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,144 | $7,160 | Implemented |
IC0282 # 03 Y:2023 | 03 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,241 | $4,067 | Not Implemented |
IC0282 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $132,518 | $1,169,610 | Not Implemented |