IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,583

matching recommendations
Reset
SIC 30 Rubber And Miscellaneous Plastics Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0315 # 09 Y:2003 09 2003 INSTALL OCCUPANCY SENSORS $1,174 $600 Implemented
SD0315 # 10 Y:2003 10 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,130 $0 Implemented
SD0315 # 11 Y:2003 11 2003 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $6,396 $10,000 Not Implemented
SD0315 # 12 Y:2003 12 2003 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES $77,000 $40,000 Implemented
SD0318 # 01 Y:2003 01 2003 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $44,624 $76,000 Not Implemented
SD0318 # 02 Y:2003 02 2003 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $12,503 $25,000 Not Implemented
SD0318 # 03 Y:2003 03 2003 INSTALL SKYLIGHTS $12,438 $8,500 Not Implemented
SD0318 # 04 Y:2003 04 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $4,018 $2,500 Implemented
SD0318 # 05 Y:2003 05 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,160 $1,680 Not Implemented
SD0318 # 06 Y:2003 06 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $739 $300 Implemented
SD0318 # 07 Y:2003 07 2003 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,100 $10,000 Not Implemented
SF0256 # 01 Y:2003 01 2003 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,773 $636 Not Implemented
SF0256 # 02 Y:2003 02 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $593 $433 Not Implemented
SF0256 # 03 Y:2003 03 2003 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $11,197 $8,880 Not Implemented
SF0256 # 04 Y:2003 04 2003 INSTALL OCCUPANCY SENSORS $2,150 $5,160 Not Implemented
SF0256 # 05 Y:2003 05 2003 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $11,466 $7,440 Not Implemented
SF0256 # 06 Y:2003 06 2003 RECOVER WASTE HEAT FROM EQUIPMENT $382 $1,618 Not Implemented
SF0256 # 07 Y:2003 07 2003 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $801 $5,231 Not Implemented
SF0256 # 08 Y:2003 08 2003 REUSE / RECYCLE/ SELL RUBBER PRODUCTS $975 $1,800 Not Implemented
SF0254 # 01 Y:2003 01 2003 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,176 $134 Not Implemented
SF0254 # 02 Y:2003 02 2003 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,744 $1,542 Not Implemented
SF0254 # 03 Y:2003 03 2003 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $924 $587 Not Implemented
SF0254 # 04 Y:2003 04 2003 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $678 $1,749 Not Implemented
SF0254 # 05 Y:2003 05 2003 INSTALL SKYLIGHTS $1,924 $12,971 Not Implemented
SF0254 # 06 Y:2003 06 2003 OPTIMIZE PLANT POWER FACTOR $7,343 $11,038 Not Implemented