Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
542
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SU0407 # 04 Y:2016 | 04 | 2016 | REDUCE VENTILATION AIR | $5,800 | $523 | Not Implemented |
SU0407 # 03 Y:2016 | 03 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,289 | $737 | Not Implemented |
SU0407 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,191 | $1,340 | Not Implemented |
SU0407 # 01 Y:2016 | 01 | 2016 | DISCONNECT BALLASTS | $76 | $0 | Not Implemented |
SU0401 # 01 Y:2015 | 01 | 2015 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,820 | $0 | Implemented |
SU0401 # 02 Y:2015 | 02 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $3,274 | $1,580 | Implemented |
SU0401 # 03 Y:2015 | 03 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $964 | $469 | Not Implemented |
SU0401 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $383 | $240 | Implemented |
SU0401 # 06 Y:2015 | 06 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $218 | $404 | Not Implemented |
SU0401 # 05 Y:2015 | 05 | 2015 | REPLACE BOILER | $11,805 | $10,686 | Implemented |
SU0401 # 08 Y:2015 | 08 | 2015 | USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR | $9,780 | $49,000 | Not Implemented |
SU0401 # 07 Y:2015 | 07 | 2015 | ELIMINATE/REDUCE AN OPERATION | $956 | $3,709 | Not Implemented |
SU0389 # 10 Y:2015 | 10 | 2015 | UPGRADE OBSOLETE EQUIPMENT | $257 | $1,070 | Implemented |
SU0389 # 09 Y:2015 | 09 | 2015 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $372 | $804 | Implemented |
SU0389 # 08 Y:2015 | 08 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $119 | $123 | Implemented |
SU0389 # 07 Y:2015 | 07 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,064 | $2,148 | Implemented |
SU0389 # 06 Y:2015 | 06 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,731 | $2,974 | Implemented |
SU0389 # 05 Y:2015 | 05 | 2015 | INSTALL OCCUPANCY SENSORS | $402 | $158 | Not Implemented |
SU0389 # 04 Y:2015 | 04 | 2015 | IMPLEMENT A REGULAR MAINTENANCE PROGRAM TO REDUCE EMISSIONS FROM LEAKY VALVES AND PIPE FITTINGS | $10,554 | $3,085 | Implemented |
SU0389 # 03 Y:2015 | 03 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $516 | $0 | Implemented |
SU0389 # 02 Y:2015 | 02 | 2015 | DISCONNECT BALLASTS | $1,418 | $0 | Not Implemented |
SU0389 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,788 | $0 | Not Implemented |
SU0388 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $333 | $340 | Not Implemented |
SU0388 # 02 Y:2015 | 02 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,375 | $2,025 | Implemented |
SU0388 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,565 | $1,340 | Implemented |