Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,096
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0575 # 12 Y:2021 | 12 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,554 | $6,764 | Implemented |
UU0190 # 01 Y:2021 | 01 | 2021 | INSULATE BARE EQUIPMENT | $9,772 | $5,582 | Not Implemented |
UU0190 # 02 Y:2021 | 02 | 2021 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $8,939 | $3,000 | Not Implemented |
UU0190 # 03 Y:2021 | 03 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,184 | $2,500 | Not Implemented |
UU0190 # 04 Y:2021 | 04 | 2021 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $2,942 | $2,900 | Not Implemented |
UU0190 # 05 Y:2021 | 05 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,058 | $778 | Not Implemented |
CO0741 # 01 Y:2021 | 01 | 2021 | USE SOLAR HEAT TO MAKE ELECTRICTY | $48,927 | $491,439 | Not Implemented |
CO0741 # 02 Y:2021 | 02 | 2021 | INSTALL WIND POWERED ELECTRIC GENERATOR | $38,875 | $547,800 | Not Implemented |
CO0741 # 03 Y:2021 | 03 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $15,984 | $0 | Implemented |
CO0741 # 04 Y:2021 | 04 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $14,264 | $21,000 | Implemented |
CO0741 # 05 Y:2021 | 05 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,303 | $3,500 | Implemented |
CO0741 # 06 Y:2021 | 06 | 2021 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,794 | $0 | Implemented |
CO0741 # 07 Y:2021 | 07 | 2021 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $51,454 | $3,624 | Implemented |
CO0741 # 08 Y:2021 | 08 | 2021 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $7,987 | $33,250 | Not Implemented |
DL0196 # 01 Y:2021 | 01 | 2021 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $5,944 | $6,452 | Not Implemented |
DL0196 # 02 Y:2021 | 02 | 2021 | TURN OFF EQUIPMENT WHEN NOT IN USE | $849 | $0 | Implemented |
DL0196 # 03 Y:2021 | 03 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $509 | $165 | Not Implemented |
DL0196 # 04 Y:2021 | 04 | 2021 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $110 | $20 | Not Implemented |
DL0196 # 05 Y:2021 | 05 | 2021 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,762 | $1,037 | Not Implemented |
DL0196 # 06 Y:2021 | 06 | 2021 | INSULATE BARE EQUIPMENT | $1,842 | $2,864 | Implemented |
DL0196 # 07 Y:2021 | 07 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,469 | $18,418 | Implemented |
DL0196 # 08 Y:2021 | 08 | 2021 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $5,629 | $13,777 | Not Implemented |
LE0515 # 01 Y:2021 | 01 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,213 | $0 | Implemented |
LE0515 # 02 Y:2021 | 02 | 2021 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,306 | $1,500 | Implemented |
LE0515 # 03 Y:2021 | 03 | 2021 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,441 | $1,500 | Implemented |