Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17,096
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0185 # 01 Y:1983 | 01 | 1983 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $9,050 | $1,200 | Not Implemented |
GT0185 # 02 Y:1983 | 02 | 1983 | MINIMIZE WATER USAGE | $8,324 | $3,000 | Not Implemented |
GT0185 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,683 | $4,700 | Not Implemented |
GT0185 # 04 Y:1983 | 04 | 1983 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $11,993 | $9,000 | Not Implemented |
GT0185 # 05 Y:1983 | 05 | 1983 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $21,913 | $97,700 | Not Implemented |
GT0185 # 06 Y:1983 | 06 | 1983 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,729 | $0 | Not Implemented |
GT0185 # 07 Y:1983 | 07 | 1983 | USE DIRECT AIR SUPPLY TO EXHAUST HOODS | $11,340 | $9,000 | Not Implemented |
GT0185 # 08 Y:1983 | 08 | 1983 | USE OPTIMUM THICKNESS INSULATION | $9,548 | $8,200 | Not Implemented |
GT0181 # 01 Y:1983 | 01 | 1983 | REDUCE LOAD ON ELECTRICAL CONDUCTOR TO REDUCE HEATING LOSSES | $20,000 | $28,000 | Not Implemented |
GT0181 # 02 Y:1983 | 02 | 1983 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $10,422 | $9,000 | Not Implemented |
GT0181 # 03 Y:1983 | 03 | 1983 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $12,800 | $65,900 | Not Implemented |
GT0181 # 04 Y:1983 | 04 | 1983 | OPTIMIZE PLANT POWER FACTOR | $5,360 | $12,000 | Not Implemented |
GT0181 # 05 Y:1983 | 05 | 1983 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,800 | $1,000 | Not Implemented |
OK0094 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $764 | $183 | Not Implemented |
OK0094 # 02 Y:1983 | 02 | 1983 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $19 | $45 | Not Implemented |
OK0094 # 03 Y:1983 | 03 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $988 | $800 | Not Implemented |
OK0094 # 04 Y:1983 | 04 | 1983 | REPAIR AND ELIMINATE STEAM LEAKS | $2,438 | $1,127 | Implemented |
OK0094 # 05 Y:1983 | 05 | 1983 | OPTIMIZE PLANT POWER FACTOR | $728 | $545 | Not Implemented |
OK0094 # 06 Y:1983 | 06 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $263 | $200 | Implemented |
OK0094 # 07 Y:1983 | 07 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $24 | $30 | Not Implemented |
OK0094 # 08 Y:1983 | 08 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $156 | $47 | Implemented |
OK0094 # 09 Y:1983 | 09 | 1983 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $87 | $51 | Implemented |
OK0094 # 10 Y:1983 | 10 | 1983 | INSTALL / REPAIR INSULATION ON STEAM LINES | $97 | $49 | Not Implemented |
OK0084 # 01 Y:1983 | 01 | 1983 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $4,150 | $913 | Not Implemented |
OK0084 # 02 Y:1983 | 02 | 1983 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $115 | $187 | Implemented |