Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
651
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0308 # 09 Y:2017 | 09 | 2017 | INSTALL OCCUPANCY SENSORS | $540 | $885 | Implemented |
MI0306 # 01 Y:2017 | 01 | 2017 | MAKE ICE DURING OFF PEAK HOURS FOR COOLING | $53,389 | $312,800 | Not Implemented |
MI0306 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,953 | $33,615 | Not Implemented |
MI0306 # 03 Y:2017 | 03 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,316 | $240 | Implemented |
MI0306 # 04 Y:2017 | 04 | 2017 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $4,609 | $8,095 | Not Implemented |
MI0306 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,512 | $14,280 | Not Implemented |
MI0306 # 06 Y:2017 | 06 | 2017 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,286 | $9,500 | Not Implemented |
MI0306 # 07 Y:2017 | 07 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,134 | $1,660 | Implemented |
MI0306 # 08 Y:2017 | 08 | 2017 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $3,893 | $8,040 | Not Implemented |
MI0306 # 09 Y:2017 | 09 | 2017 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,238 | $650 | Implemented |
MI0306 # 10 Y:2017 | 10 | 2017 | INSTALL OCCUPANCY SENSORS | $1,858 | $177 | Implemented |
MI0306 # 11 Y:2017 | 11 | 2017 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $711 | $120 | Implemented |
MI0306 # 12 Y:2017 | 12 | 2017 | INSTALL OCCUPANCY SENSORS | $612 | $1,630 | Implemented |
MI0295 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,797 | $59,670 | Not Implemented |
MI0295 # 02 Y:2016 | 02 | 2016 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $26,678 | $80,000 | Not Implemented |
MI0295 # 03 Y:2016 | 03 | 2016 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $17,275 | $4,471 | Not Implemented |
MI0295 # 04 Y:2016 | 04 | 2016 | USE PHOTOCELL CONTROLS | $11,307 | $10,380 | Not Implemented |
MI0295 # 05 Y:2016 | 05 | 2016 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $7,874 | $40 | Not Implemented |
MI0295 # 06 Y:2016 | 06 | 2016 | INSTALL DRY SPRINKLER SYSTEM OR OTHER METHOD TO REDUCE HEATING REQUIREMENTS | $7,334 | $4,411 | Not Implemented |
MI0295 # 07 Y:2016 | 07 | 2016 | PAY UTILITY BILLS ON TIME | $4,723 | $0 | Not Implemented |
MI0295 # 08 Y:2016 | 08 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,957 | $1,660 | Not Implemented |
MI0295 # 09 Y:2016 | 09 | 2016 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,084 | $320 | Not Implemented |
MI0295 # 10 Y:2016 | 10 | 2016 | INSTALL OCCUPANCY SENSORS | $1,284 | $683 | Not Implemented |
MI0295 # 11 Y:2016 | 11 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $448 | $640 | Not Implemented |
MI0292 # 01 Y:2016 | 01 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $38,353 | $95,355 | Implemented |