Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
496
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TT0132 # 11 Y:2014 | 11 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $6,407 | $8,750 | Implemented |
TT0132 # 12 Y:2014 | 12 | 2014 | REDUCE FLUID FLOW RATES | $893 | $1,000 | Not Implemented |
TT0132 # 13 Y:2014 | 13 | 2014 | DISCONNECT BALLASTS | $1,153 | $63 | Not Implemented |
TT0132 # 14 Y:2014 | 14 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $892 | $850 | Not Implemented |
TT0120 # 01 Y:2013 | 01 | 2013 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,400 | $85 | Implemented |
TT0120 # 02 Y:2013 | 02 | 2013 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,836 | $1,344 | Implemented |
TT0120 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,320 | $7,588 | Implemented |
TT0120 # 04 Y:2013 | 04 | 2013 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,735 | $0 | Not Implemented |
TT0121 # 01 Y:2013 | 01 | 2013 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,465 | $100 | Implemented |
TT0121 # 02 Y:2013 | 02 | 2013 | INSTALL OCCUPANCY SENSORS | $2,202 | $2,150 | Not Implemented |
TT0121 # 03 Y:2013 | 03 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $47 | $75 | Implemented |
TT0121 # 04 Y:2013 | 04 | 2013 | COMBINE UTILITY METERS | $6,476 | $12,000 | Not Implemented |
TT0121 # 05 Y:2013 | 05 | 2013 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $4,667 | $9,338 | Not Implemented |
TT0121 # 06 Y:2013 | 06 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,685 | $8,460 | Implemented |
TT0121 # 07 Y:2013 | 07 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $464 | $800 | Implemented |
TT0115 # 09 Y:2013 | 09 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $11,635 | $20,000 | Not Implemented |
TT0115 # 01 Y:2013 | 01 | 2013 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $18,000 | $50,000 | Implemented |
TT0115 # 02 Y:2013 | 02 | 2013 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $18,000 | $50,000 | Implemented |
TT0115 # 03 Y:2013 | 03 | 2013 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $21,000 | $50,000 | Not Implemented |
TT0115 # 04 Y:2013 | 04 | 2013 | OPTIMIZE PLANT POWER FACTOR | $32,990 | $129,250 | Not Implemented |
TT0115 # 05 Y:2013 | 05 | 2013 | REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT | $146,360 | $450,000 | Not Implemented |
TT0115 # 06 Y:2013 | 06 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,000 | $4,000 | Not Implemented |
TT0115 # 07 Y:2013 | 07 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,635 | $2,500 | Not Implemented |
TT0115 # 08 Y:2013 | 08 | 2013 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,984 | $20,000 | Not Implemented |
TT0085 # 01 Y:2012 | 01 | 2012 | OPTIMIZE PLANT POWER FACTOR | $142,952 | $100,850 | Not Implemented |