Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
435
matching recommendationsSIC | 30 | Rubber And Miscellaneous Plastics Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0925 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,762 | $933 | Implemented |
OK0925 # 11 Y:2015 | 11 | 2015 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $5,100 | $9,690 | Not Implemented |
OK0925 # 10 Y:2015 | 10 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,128 | $65,326 | Not Implemented |
OK0925 # 06 Y:2015 | 06 | 2015 | USE COMPRESSOR AIR FILTERS | $757 | $362 | Implemented |
OK0925 # 08 Y:2015 | 08 | 2015 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $3,748 | $9,360 | Not Implemented |
OK0925 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,255 | $71,792 | Not Implemented |
OK0925 # 09 Y:2015 | 09 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,024 | $10,944 | Not Implemented |
OK0925 # 03 Y:2015 | 03 | 2015 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $160 | $214 | Implemented |
OK0925 # 02 Y:2015 | 02 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,930 | $9,328 | Not Implemented |
OK0925 # 05 Y:2015 | 05 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $278 | $229 | Not Implemented |
OK0925 # 07 Y:2015 | 07 | 2015 | IMPROVE CLEANING EFFICIENCY BY MAINTAINING CLEANING SYSTEM | $6,933 | $5,596 | Implemented |
NC0558 # 12 Y:2015 | 12 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $320 | $1,595 | Implemented |
NC0558 # 03 Y:2015 | 03 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $16,078 | $5,000 | Implemented |
NC0558 # 11 Y:2015 | 11 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $145 | $716 | Implemented |
NC0558 # 07 Y:2015 | 07 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $63,599 | $250,000 | Not Implemented |
NC0558 # 08 Y:2015 | 08 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,031 | $227 | Implemented |
NC0558 # 04 Y:2015 | 04 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,981 | $1,000 | Not Implemented |
NC0558 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,925 | $300 | Implemented |
NC0558 # 06 Y:2015 | 06 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $44 | $120 | Not Implemented |
IP0055 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,465 | $3 | Not Implemented |
NC0558 # 01 Y:2015 | 01 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $28,923 | $17,820 | Not Implemented |
IP0055 # 03 Y:2015 | 03 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,460 | $3 | Implemented |
IP0055 # 04 Y:2015 | 04 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $1,413 | $3 | Not Implemented |
IP0055 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,177 | $86 | Implemented |
NC0558 # 05 Y:2015 | 05 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,947 | $6,425 | Implemented |