Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
55
matching recommendationsSIC | 306 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MI0446 # 03 Y:2024 | 03 | 2024 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $15,109 | $12,480 | n/a |
MI0446 # 02 Y:2024 | 02 | 2024 | UPGRADE CONVEYORS | $36,000 | $40,966 | n/a |
MI0446 # 01 Y:2024 | 01 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $103,738 | $390,000 | n/a |
UF0597 # 09 Y:2023 | 09 | 2023 | IMPROVE SPACE COMFORT CONDITIONING | $35,500 | $4,261 | Implemented |
UF0597 # 08 Y:2023 | 08 | 2023 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $51,744 | $18,218 | Implemented |
UF0597 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,699 | $4,994 | Implemented |
UF0597 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $20,876 | $14,705 | Implemented |
UF0597 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,382 | $13,706 | Implemented |
UF0597 # 05 Y:2023 | 05 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,959 | $11,134 | Implemented |
UF0597 # 02 Y:2023 | 02 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,736 | $15,722 | Implemented |
UF0597 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,612 | $25,370 | Implemented |
UF0597 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,142 | $22,000 | Implemented |
UF0509 # 06 Y:2017 | 06 | 2017 | INSTALL OCCUPANCY SENSORS | $1,241 | $1,280 | Implemented |
UF0509 # 03 Y:2017 | 03 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,560 | $0 | Implemented |
UF0509 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,130 | $3,321 | Implemented |
UF0509 # 07 Y:2017 | 07 | 2017 | AVOID CONTAMINATION OF END PIECES AND REUSE AS FEED STOCK | $42,000 | $0 | Implemented |
UF0509 # 02 Y:2017 | 02 | 2017 | UPGRADE CONTROLS ON COMPRESSORS | $4,408 | $940 | Not Implemented |
UF0509 # 04 Y:2017 | 04 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,157 | $844 | Implemented |
UF0509 # 01 Y:2017 | 01 | 2017 | INSTALL COMMON HEADER ON COMPRESSORS | $5,078 | $10,260 | Not Implemented |
MI0292 # 04 Y:2016 | 04 | 2016 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,028 | $8,642 | Not Implemented |
MI0292 # 05 Y:2016 | 05 | 2016 | INSTALL OCCUPANCY SENSORS | $4,106 | $884 | Implemented |
MI0292 # 06 Y:2016 | 06 | 2016 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,562 | $1,832 | Not Implemented |
MI0292 # 07 Y:2016 | 07 | 2016 | USE OPTIMUM THICKNESS INSULATION | $2,670 | $1,810 | Implemented |
MI0292 # 08 Y:2016 | 08 | 2016 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,585 | $670 | Not Implemented |
MI0292 # 09 Y:2016 | 09 | 2016 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $1,313 | $480 | Not Implemented |