Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,033
matching recommendationsSIC | 306 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0597 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,699 | $4,994 | Implemented |
UF0597 # 06 Y:2023 | 06 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,382 | $13,706 | Implemented |
UF0597 # 05 Y:2023 | 05 | 2023 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $3,959 | $11,134 | Implemented |
UF0597 # 04 Y:2023 | 04 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,142 | $22,000 | Implemented |
UF0597 # 03 Y:2023 | 03 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,612 | $25,370 | Implemented |
UF0597 # 02 Y:2023 | 02 | 2023 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,736 | $15,722 | Implemented |
UF0597 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $20,876 | $14,705 | Implemented |
TR0041 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,679 | $3,857 | n/a |
TR0041 # 02 Y:2022 | 02 | 2022 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $28,659 | $27,941 | n/a |
TR0041 # 03 Y:2022 | 03 | 2022 | UPGRADE OBSOLETE EQUIPMENT | $17,496 | $200,000 | n/a |
UU0219 # 06 Y:2023 | 06 | 2023 | INSTALL ISOLATION TRANSFORMER ON ADJUSTABLE FREQUENCY DRIVE | $1,035 | $729 | Not Implemented |
UU0219 # 05 Y:2023 | 05 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,272 | $172 | Not Implemented |
UU0219 # 04 Y:2023 | 04 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,850 | $18,236 | Not Implemented |
UU0219 # 03 Y:2023 | 03 | 2023 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,350 | $2,350 | Not Implemented |
UU0219 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,112 | $13,345 | Implemented |
UU0219 # 01 Y:2023 | 01 | 2023 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $242,311 | $1,768,555 | Not Implemented |
NL0078 # 06 Y:2023 | 06 | 2023 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $658 | $80 | n/a |
NL0078 # 05 Y:2023 | 05 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $812 | $2,080 | n/a |
NL0078 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,587 | $2,300 | n/a |
NL0078 # 03 Y:2023 | 03 | 2023 | UPGRADE CONTROLS ON COMPRESSORS | $6,550 | $20,000 | n/a |
NL0078 # 02 Y:2023 | 02 | 2023 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $10,358 | $17,280 | n/a |
NL0078 # 01 Y:2023 | 01 | 2023 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $31,345 | $100,000 | n/a |
NL0078 # 07 Y:2023 | 07 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $270 | $415 | n/a |
NL0078 # 08 Y:2023 | 08 | 2023 | METER WASTE WATER | $128 | $250 | n/a |
TR0037 # 01 Y:2022 | 01 | 2022 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $5,441 | $10,000 | Not Implemented |