Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,537
matching recommendationsSIC | 3069 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0447 # 05 Y:2010 | 05 | 2010 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $6,801 | $42,100 | Not Implemented |
IA0447 # 06 Y:2010 | 06 | 2010 | REPLACE BOILER | $29,283 | $53,900 | Implemented |
IA0447 # 07 Y:2010 | 07 | 2010 | SUBSTITUTE HOT PROCESS FLUIDS FOR STEAM | $525 | $5,000 | Implemented |
DL0046 # 01 Y:2010 | 01 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,503 | $0 | Not Implemented |
DL0046 # 02 Y:2010 | 02 | 2010 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,940 | $0 | Not Implemented |
DL0046 # 03 Y:2010 | 03 | 2010 | INSULATE BARE EQUIPMENT | $7,292 | $520 | Not Implemented |
DL0046 # 04 Y:2010 | 04 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $4,168 | $1,500 | Implemented |
DL0046 # 05 Y:2010 | 05 | 2010 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,619 | $10,000 | Implemented |
DL0046 # 06 Y:2010 | 06 | 2010 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,295 | $23,738 | Implemented |
DL0046 # 07 Y:2010 | 07 | 2010 | DE-ENERGIZE EXCESS TRANSFORMER CAPACITY | $785 | $2,410 | Not Implemented |
IA0441 # 01 Y:2009 | 01 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,701 | $680 | Not Implemented |
IA0441 # 02 Y:2009 | 02 | 2009 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $7,759 | $17,051 | Not Implemented |
IA0441 # 03 Y:2009 | 03 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,444 | $702 | Implemented |
IA0441 # 04 Y:2009 | 04 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,935 | $825 | Not Implemented |
IA0441 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,456 | $650 | Not Implemented |
IA0441 # 06 Y:2009 | 06 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,420 | $1,820 | Not Implemented |
IA0441 # 07 Y:2009 | 07 | 2009 | INSTALL OCCUPANCY SENSORS | $853 | $479 | Implemented |
IA0441 # 08 Y:2009 | 08 | 2009 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,129 | $760 | Implemented |
IA0441 # 09 Y:2009 | 09 | 2009 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $49,777 | $70,000 | Not Implemented |
IA0441 # 10 Y:2009 | 10 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $25,097 | $27,000 | Implemented |
IA0441 # 11 Y:2009 | 11 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $16,289 | $16,600 | Implemented |
GT0865 # 01 Y:2009 | 01 | 2009 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $23,450 | $0 | Not Implemented |
GT0865 # 02 Y:2009 | 02 | 2009 | REDUCE FLUID FLOW RATES | $3,226 | $1,220 | Not Implemented |
GT0865 # 03 Y:2009 | 03 | 2009 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $5,697 | $1,100 | Not Implemented |
GT0865 # 04 Y:2009 | 04 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,003 | $1,920 | Not Implemented |