Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 3069 | Fabricated Rubber Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0302 # 07 Y:1989 | 07 | 1989 | OPTIMIZE PLANT POWER FACTOR | $955 | $2,600 | Not Implemented |
OK0302 # 01 Y:1989 | 01 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $484 | $167 | Implemented |
OK0302 # 02 Y:1989 | 02 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $491 | $640 | Not Implemented |
OK0302 # 03 Y:1989 | 03 | 1989 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $134 | $280 | Implemented |
OK0302 # 04 Y:1989 | 04 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $310 | $487 | Not Implemented |
OK0302 # 05 Y:1989 | 05 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $373 | $630 | Implemented |
OK0302 # 06 Y:1989 | 06 | 1989 | INSULATE BARE EQUIPMENT | $265 | $120 | Not Implemented |
WI0047 # 06 Y:1989 | 06 | 1989 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,766 | $2,100 | Implemented |
LT0142 # 01 Y:1989 | 01 | 1989 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $214,983 | $77,904 | Not Implemented |
WI0047 # 05 Y:1989 | 05 | 1989 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,913 | $3,600 | Implemented |
WI0047 # 04 Y:1989 | 04 | 1989 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $1,836 | $0 | Not Implemented |
WI0047 # 03 Y:1989 | 03 | 1989 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $238 | $0 | Implemented |
WI0047 # 02 Y:1989 | 02 | 1989 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $3,901 | $1,300 | Implemented |
WI0047 # 01 Y:1989 | 01 | 1989 | IMPROVE LUBRICATION PRACTICES | $3,210 | $500 | Implemented |
LT0142 # 08 Y:1989 | 08 | 1989 | REPAIR AND ELIMINATE STEAM LEAKS | $3,193 | $224 | Implemented |
LT0142 # 07 Y:1989 | 07 | 1989 | INSTALL / REPAIR INSULATION ON STEAM LINES | $423 | $100 | Implemented |
LT0142 # 06 Y:1989 | 06 | 1989 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,250 | $754 | Not Implemented |
LT0142 # 05 Y:1989 | 05 | 1989 | INSTALL TIMERS AND/OR THERMOSTATS | $3,092 | $200 | Implemented |
LT0142 # 04 Y:1989 | 04 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,470 | $400 | Implemented |
LT0142 # 03 Y:1989 | 03 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,008 | $442 | Implemented |
LT0142 # 02 Y:1989 | 02 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $7,542 | $442 | Implemented |