Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
64
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UK1912 # 02 Y:2019 | 02 | 2019 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,541 | $0 | Implemented |
UK1912 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $28,487 | $2,150 | Implemented |
UK1912 # 06 Y:2019 | 06 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,364 | $30,555 | Implemented |
UK1912 # 09 Y:2019 | 09 | 2019 | TURN OFF EQUIPMENT WHEN NOT IN USE | $86,767 | $5,000 | Implemented |
UK1504 # 09 Y:2015 | 09 | 2015 | INSULATE BARE EQUIPMENT | $2,405 | $810 | Implemented |
UK1504 # 10 Y:2015 | 10 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,473 | $0 | Implemented |
UK1504 # 07 Y:2015 | 07 | 2015 | USE ONLY CERTIFIED MOTOR REPAIR SHOPS | $6,448 | $6,381 | Implemented |
UK1504 # 05 Y:2015 | 05 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,588 | $1,750 | Implemented |
UK1504 # 03 Y:2015 | 03 | 2015 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $453 | $405 | Implemented |
UK1504 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,819 | $0 | Implemented |
UK1503 # 07 Y:2015 | 07 | 2015 | MAINTAIN AIR FILTERS BY CLEANING OR REPLACEMENT | $1,126 | $1,460 | Implemented |
UK1503 # 11 Y:2015 | 11 | 2015 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $62,362 | $45,000 | Implemented |
UK1503 # 09 Y:2015 | 09 | 2015 | INSULATE BARE EQUIPMENT | $17,159 | $9,380 | Implemented |
UK1503 # 10 Y:2015 | 10 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $2,034 | $2,460 | Implemented |
UK1503 # 01 Y:2015 | 01 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $605 | $960 | Implemented |
UK1503 # 02 Y:2015 | 02 | 2015 | USE PHOTOCELL CONTROLS | $3,487 | $4,040 | Implemented |
UK1503 # 06 Y:2015 | 06 | 2015 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $16,001 | $5,000 | Implemented |
UK1503 # 08 Y:2015 | 08 | 2015 | MINIMIZE WATER USAGE | $556 | $2,470 | Implemented |
UK1503 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $945 | $520 | Implemented |
UK1503 # 05 Y:2015 | 05 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,831 | $3,000 | Implemented |
UK1503 # 04 Y:2015 | 04 | 2015 | UPGRADE CONTROLS ON COMPRESSORS | $5,138 | $3,760 | Implemented |
UL0226 # 03 Y:1999 | 03 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,134 | $0 | Implemented |
UL0226 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,020 | $522 | Implemented |
UL0226 # 04 Y:1999 | 04 | 1999 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $433 | $930 | Implemented |
UL0206 # 03 Y:1998 | 03 | 1998 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $28,180 | $0 | Implemented |