Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
90
matching recommendationsSIC | 308 | Miscellaneous Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0147 # 05 Y:1984 | 05 | 1984 | INSTALL / REPAIR INSULATION ON CONDENSATE LINES | $588 | $680 | Implemented |
UD0147 # 02 Y:1984 | 02 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $521 | $600 | Implemented |
UD0147 # 01 Y:1984 | 01 | 1984 | USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING | $5,049 | $2,250 | Implemented |
UD0147 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,487 | $346 | Implemented |
UD0147 # 04 Y:1984 | 04 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,055 | $700 | Implemented |
UD0144 # 01 Y:1984 | 01 | 1984 | USE SMALL NUMBER OF HIGH OUTPUT UNITS INSTEAD OF MANY SMALL INEFFICIENT UNITS | $104,097 | $320,000 | Implemented |
TN0229 # 03 Y:1984 | 03 | 1984 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $786 | $800 | Not Implemented |
TN0229 # 06 Y:1984 | 06 | 1984 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $136 | $0 | Implemented |
MA0009 # 02 Y:1984 | 02 | 1984 | INSTALL SET-BACK TIMERS | $1,183 | $200 | Implemented |
TN0229 # 04 Y:1984 | 04 | 1984 | INSTALL SET-BACK TIMERS | $1,802 | $0 | Not Implemented |
MA0009 # 03 Y:1984 | 03 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $100 | $0 | Implemented |
TN0229 # 05 Y:1984 | 05 | 1984 | INSULATE BARE EQUIPMENT | $96 | $26 | Implemented |
TN0229 # 01 Y:1984 | 01 | 1984 | INSULATE BARE EQUIPMENT | $3,128 | $340 | Not Implemented |
TN0229 # 02 Y:1984 | 02 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $2,384 | $360 | Not Implemented |
MA0009 # 01 Y:1984 | 01 | 1984 | INSULATE BARE EQUIPMENT | $2,206 | $2,100 | Not Implemented |
ST0005 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,350 | $1,354 | Implemented |
GT0229 # 07 Y:1984 | 07 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,404 | $1,270 | Implemented |
GT0229 # 08 Y:1984 | 08 | 1984 | INSTALL SET-BACK TIMERS | $330 | $0 | Implemented |
GT0229 # 06 Y:1984 | 06 | 1984 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $645 | $368 | Implemented |
GT0229 # 09 Y:1984 | 09 | 1984 | INSULATE BARE EQUIPMENT | $50 | $150 | Implemented |
GT0229 # 05 Y:1984 | 05 | 1984 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $919 | $500 | Not Implemented |
MA0007 # 01 Y:1984 | 01 | 1984 | INSTALL SET-BACK TIMERS | $543 | $650 | Implemented |
MA0007 # 03 Y:1984 | 03 | 1984 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $34,692 | $70,668 | Not Implemented |
ST0006 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,274 | $537 | Implemented |
ST0005 # 08 Y:1984 | 08 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $926 | $269 | Implemented |