IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

143

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TN0371 # 05 Y:1989 05 1989 RECOVER WASTE HEAT FROM EQUIPMENT $2,475 $3,050 Implemented
TN0371 # 06 Y:1989 06 1989 INSULATE BARE EQUIPMENT $7,555 $536 Implemented
TN0371 # 07 Y:1989 07 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,305 $660 Implemented
TN0371 # 08 Y:1989 08 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,659 $0 Implemented
RU0059 # 01 Y:1989 01 1989 REDESIGN PROCESS $81,076 $84,000 Not Implemented
RU0059 # 02 Y:1989 02 1989 OPTIMIZE PLANT POWER FACTOR $36,000 $39,000 Implemented
RU0059 # 03 Y:1989 03 1989 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $11,797 $16,740 Not Implemented
RU0059 # 04 Y:1989 04 1989 ISOLATE HOT OR COLD EQUIPMENT $6,424 $11,590 Not Implemented
RU0059 # 05 Y:1989 05 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,490 $479 Not Implemented
WI0059 # 01 Y:1989 01 1989 IMPROVE LUBRICATION PRACTICES $12,658 $0 Not Implemented
WI0059 # 02 Y:1989 02 1989 TURN OFF EQUIPMENT WHEN NOT IN USE $8,983 $800 Implemented
WI0059 # 03 Y:1989 03 1989 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $7,916 $5,000 Implemented
WI0059 # 04 Y:1989 04 1989 RECOVER WASTE HEAT FROM EQUIPMENT $5,025 $3,000 Not Implemented
WI0059 # 05 Y:1989 05 1989 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS $2,400 $3,750 Implemented
WI0059 # 06 Y:1989 06 1989 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,517 $2,000 Implemented
WI0059 # 07 Y:1989 07 1989 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,374 $0 Implemented
WI0059 # 08 Y:1989 08 1989 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $929 $1,000 Not Implemented
WI0059 # 09 Y:1989 09 1989 INSTALL SET-BACK TIMERS $449 $400 Not Implemented
WI0059 # 10 Y:1989 10 1989 INSULATE BARE EQUIPMENT $258 $175 Not Implemented
OK0281 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $200 $89 Implemented
OK0281 # 02 Y:1989 02 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $123 $240 Implemented
OK0281 # 03 Y:1989 03 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,427 $1,500 Implemented
OK0281 # 04 Y:1989 04 1989 REPAIR AND ELIMINATE STEAM LEAKS $26,441 $5,000 Implemented
OK0281 # 05 Y:1989 05 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $190 $448 Implemented
OK0281 # 06 Y:1989 06 1989 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $2,803 $3,680 Implemented