IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

492

matching recommendations
Reset
SIC 308 Miscellaneous Plastics Products, Nec
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0348 # 05 Y:1995 05 1995 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY $310 $1,745 Implemented
CO0348 # 04 Y:1995 04 1995 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS $1,425 $3,020 Not Implemented
CO0348 # 03 Y:1995 03 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,260 $400 Implemented
CO0348 # 02 Y:1995 02 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,870 $0 Not Implemented
CO0348 # 01 Y:1995 01 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,400 $8,810 Implemented
MA0349 # 01 Y:1995 01 1995 INSULATE BARE EQUIPMENT $47,119 $20,700 Implemented
MA0349 # 02 Y:1995 02 1995 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $25,737 $27,186 Not Implemented
MA0349 # 03 Y:1995 03 1995 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $858 $1,700 Implemented
MA0349 # 04 Y:1995 04 1995 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $777 $2,600 Not Implemented
MA0349 # 05 Y:1995 05 1995 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $571 $127 Not Implemented
MS0042 # 06 Y:1995 06 1995 USE RADIANT HEATER FOR SPOT HEATING $7,400 $3,132 Implemented
MS0042 # 05 Y:1995 05 1995 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $13,524 $1,400 Implemented
MS0042 # 04 Y:1995 04 1995 RECOVER WASTE HEAT FROM EQUIPMENT $1,264 $4,785 Implemented
MS0042 # 03 Y:1995 03 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $348 $778 Implemented
MS0042 # 02 Y:1995 02 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $12,635 $0 Implemented
MS0042 # 01 Y:1995 01 1995 OPTIMIZE PLANT POWER FACTOR $64,604 $60,000 Implemented
UD0474 # 01 Y:1995 01 1995 OPTIMIZE PLANT POWER FACTOR $17,216 $20,000 Implemented
UD0474 # 02 Y:1995 02 1995 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $12,332 $14,000 Not Implemented
UD0474 # 03 Y:1995 03 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,945 $0 Not Implemented
UD0474 # 04 Y:1995 04 1995 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,696 $2,857 Not Implemented
UD0474 # 05 Y:1995 05 1995 DISCONNECT BALLASTS $4,012 $300 Implemented
UD0474 # 06 Y:1995 06 1995 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $8,825 $2,000 Not Implemented
OR0250 # 01 Y:1995 01 1995 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER $16,311 $2,000 Implemented
OR0250 # 02 Y:1995 02 1995 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR $5,252 $6,500 Not Implemented
OR0250 # 03 Y:1995 03 1995 TURN OFF EQUIPMENT WHEN NOT IN USE $2,300 $600 Not Implemented