Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
221
matching recommendationsSIC | 3082 | Unsupported Plastics Profile Shapes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ME0272 # 07 Y:1999 | 07 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $5,265 | $0 | Implemented |
ME0272 # 08 Y:1999 | 08 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,172 | $5,760 | Implemented |
ME0272 # 09 Y:1999 | 09 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,760 | $7,122 | Implemented |
ME0272 # 10 Y:1999 | 10 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,141 | $7,579 | Not Implemented |
ME0272 # 11 Y:1999 | 11 | 1999 | INSULATE BARE EQUIPMENT | $1,899 | $1,260 | Implemented |
HO0209 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $44,002 | $55,668 | Not Implemented |
HO0209 # 02 Y:1999 | 02 | 1999 | INSTALL OCCUPANCY SENSORS | $1,005 | $1,600 | Implemented |
HO0209 # 03 Y:1999 | 03 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,540 | $570 | Implemented |
HO0209 # 04 Y:1999 | 04 | 1999 | USE OPTIMUM THICKNESS INSULATION | $24,609 | $13,620 | Not Implemented |
HO0209 # 05 Y:1999 | 05 | 1999 | INSULATE BARE EQUIPMENT | $3,541 | $1,468 | Not Implemented |
HO0209 # 06 Y:1999 | 06 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $39,910 | $63,000 | Not Implemented |
HO0209 # 07 Y:1999 | 07 | 1999 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $3,225 | $8,000 | Not Implemented |
HO0209 # 08 Y:1999 | 08 | 1999 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $3,797 | $800 | Not Implemented |
HO0209 # 09 Y:1999 | 09 | 1999 | RECOVER AND REUSE COOLING WATER | $28,000 | $70,000 | Not Implemented |
KU0504 # 01 Y:1998 | 01 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $14,180 | $10,050 | Implemented |
KU0504 # 02 Y:1998 | 02 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,210 | $4,420 | Implemented |
KU0504 # 03 Y:1998 | 03 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,240 | $390 | Not Implemented |
KU0504 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $840 | $350 | Implemented |
KU0504 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $450 | $1,020 | Implemented |
KU0504 # 06 Y:1998 | 06 | 1998 | RECOVER AND REUSE WASTE MATERIAL | $22,040 | $570 | Not Implemented |
KU0504 # 07 Y:1998 | 07 | 1998 | INSTALL EQUIPMENT TO MOVE PRODUCT | $43,400 | $82,500 | Not Implemented |
KU0504 # 08 Y:1998 | 08 | 1998 | $8,520 | $8,480 | Implemented | |
KU0504 # 09 Y:1998 | 09 | 1998 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $6,820 | $18,750 | Implemented |
SF0084 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $606 | $464 | Implemented |
SF0084 # 02 Y:1996 | 02 | 1996 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,317 | $2,110 | Implemented |