Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
27
matching recommendationsSIC | 3082 | Unsupported Plastics Profile Shapes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0807 # 04 Y:2009 | 04 | 2009 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,604 | $1,000 | Not Implemented |
UD0807 # 17 Y:2009 | 17 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,776 | $2,533 | Implemented |
UD0807 # 16 Y:2009 | 16 | 2009 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $2,970 | $2,000 | Not Implemented |
UD0807 # 15 Y:2009 | 15 | 2009 | INSULATE BARE EQUIPMENT | $3,086 | $2,700 | Not Implemented |
UD0807 # 14 Y:2009 | 14 | 2009 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $4,896 | $0 | Not Implemented |
UD0807 # 13 Y:2009 | 13 | 2009 | MINIMIZE WATER USAGE | $5,548 | $5,000 | Not Implemented |
UD0807 # 12 Y:2009 | 12 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,249 | $4,614 | Implemented |
UD0807 # 11 Y:2009 | 11 | 2009 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $9,719 | $23,924 | Not Implemented |
UD0807 # 10 Y:2009 | 10 | 2009 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $10,853 | $0 | Not Implemented |
UD0807 # 09 Y:2009 | 09 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,425 | $8,602 | Implemented |
UD0807 # 08 Y:2009 | 08 | 2009 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $22,644 | $0 | Not Implemented |
UD0807 # 07 Y:2009 | 07 | 2009 | OPTIMIZE PLANT POWER FACTOR | $78,142 | $100,000 | Not Implemented |
UD0807 # 06 Y:2009 | 06 | 2009 | UPGRADE CONTROLS ON COMPRESSORS | $1,564 | $7,000 | Not Implemented |
UD0807 # 05 Y:2009 | 05 | 2009 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $12,056 | $52,550 | Not Implemented |
UD0807 # 03 Y:2009 | 03 | 2009 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $65,548 | $15,550 | Not Implemented |
UD0807 # 02 Y:2009 | 02 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,575 | $1,000 | Implemented |
UD0807 # 01 Y:2009 | 01 | 2009 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $11,275 | $2,000 | Implemented |
BD0362 # 01 Y:2009 | 01 | 2009 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,931 | $36,000 | Implemented |
BD0362 # 10 Y:2009 | 10 | 2009 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,248 | $520 | Implemented |
BD0362 # 09 Y:2009 | 09 | 2009 | USE POWER DURING OFF-PEAK PERIODS | $15,684 | $2,000 | Not Implemented |
BD0362 # 08 Y:2009 | 08 | 2009 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $200 | $0 | Not Implemented |
BD0362 # 07 Y:2009 | 07 | 2009 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $7,156 | $60,000 | Not Implemented |
BD0362 # 06 Y:2009 | 06 | 2009 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,913 | $3,300 | Implemented |
BD0362 # 05 Y:2009 | 05 | 2009 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,945 | $2,900 | Implemented |
BD0362 # 04 Y:2009 | 04 | 2009 | USE SYNTHETIC LUBRICANT | $1,202 | $300 | Implemented |