Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
Reset
SIC 3083 Laminated Plastics Plate & Sheet
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OK0742 # 05 Y:2007 05 2007 INSULATE BARE EQUIPMENT $2,516 $3,910 Implemented
OK0742 # 04 Y:2007 04 2007 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $2,966 $5,529 Not Implemented
OK0742 # 03 Y:2007 03 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,664 $275 Implemented
OK0742 # 02 Y:2007 02 2007 RECOVER WASTE HEAT FROM EQUIPMENT $2,095 $3,851 Not Implemented
OK0742 # 01 Y:2007 01 2007 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $30,095 $79,680 Not Implemented
OK0291 # 03 Y:1989 03 1989 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $973 $909 Implemented
OK0291 # 09 Y:1989 09 1989 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,262 $100 Implemented
OK0291 # 08 Y:1989 08 1989 COVER OPEN TANKS $360 $955 Not Implemented
OK0291 # 07 Y:1989 07 1989 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $844 $1,500 Implemented
OK0291 # 06 Y:1989 06 1989 INSTALL TURBULATORS $1,310 $2,450 Not Implemented
OK0291 # 05 Y:1989 05 1989 INSTALL / REPAIR INSULATION ON CONDENSATE LINES $356 $480 Not Implemented
OK0291 # 04 Y:1989 04 1989 IMPROVE LUBRICATION PRACTICES $4,974 $0 Implemented
OK0291 # 02 Y:1989 02 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $7,376 $18,000 Not Implemented
OK0291 # 01 Y:1989 01 1989 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,092 $668 Implemented
KU0103 # 01 Y:1983 01 1983 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $814 $862 Not Implemented
KU0103 # 10 Y:1983 10 1983 INSULATE BARE EQUIPMENT $4,862 $2,500 Not Implemented
KU0103 # 09 Y:1983 09 1983 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $81 $0 Not Implemented
KU0103 # 08 Y:1983 08 1983 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $1,369 $200 Not Implemented
KU0103 # 07 Y:1983 07 1983 INSTALL TIMERS AND/OR THERMOSTATS $1,466 $89 Not Implemented
KU0103 # 06 Y:1983 06 1983 SHUT OFF PILOTS IN STANDBY EQUIPMENT $85 $0 Not Implemented
KU0103 # 05 Y:1983 05 1983 INSTALL AUTOMATIC STACK DAMPER $335 $450 Not Implemented
KU0103 # 04 Y:1983 04 1983 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $115 $180 Not Implemented
KU0103 # 02 Y:1983 02 1983 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,030 $100 Not Implemented