Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
21
matching recommendationsSIC | 3083 | Laminated Plastics Plate & Sheet |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ND0323 # 02 Y:1999 | 02 | 1999 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $3,731 | $250 | Implemented |
ND0323 # 12 Y:1999 | 12 | 1999 | USE OPTIMUM TEMPERATURE | $32 | $10 | Implemented |
ND0323 # 11 Y:1999 | 11 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $106 | $200 | Implemented |
ND0323 # 10 Y:1999 | 10 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $109 | $360 | Not Implemented |
ND0323 # 09 Y:1999 | 09 | 1999 | CONVERT TO AQUEOUS CLEANING SYSTEM | $114 | $100 | Not Implemented |
ND0323 # 08 Y:1999 | 08 | 1999 | INSTALL OCCUPANCY SENSORS | $256 | $600 | Implemented |
ND0323 # 07 Y:1999 | 07 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $670 | $140 | Implemented |
ND0323 # 06 Y:1999 | 06 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $736 | $1,746 | Not Implemented |
ND0323 # 05 Y:1999 | 05 | 1999 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,064 | $500 | Not Implemented |
ND0323 # 04 Y:1999 | 04 | 1999 | PURCHASE RE-CONDITIONED MATERIAL INSTEAD OF NEW | $546 | $991 | Implemented |
ND0323 # 03 Y:1999 | 03 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $2,584 | $0 | Implemented |
ND0323 # 01 Y:1999 | 01 | 1999 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $7,589 | $40,800 | Not Implemented |
HO0193 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,758 | $16,993 | Implemented |
HO0193 # 09 Y:1999 | 09 | 1999 | REDUCE DEFECTS BY REDUCING PRODUCT TIPPING | $5,000 | $3,000 | Not Implemented |
HO0193 # 08 Y:1999 | 08 | 1999 | REDUCE DEFECTS BY REDUCING PRODUCT TIPPING | $2,000 | $10,000 | Not Implemented |
HO0193 # 07 Y:1999 | 07 | 1999 | REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS | $1,872 | $3,500 | Not Implemented |
HO0193 # 06 Y:1999 | 06 | 1999 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,000 | $300 | Implemented |
HO0193 # 05 Y:1999 | 05 | 1999 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $825 | $2,000 | Implemented |
HO0193 # 04 Y:1999 | 04 | 1999 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $395 | $400 | Implemented |
HO0193 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,524 | $360 | Implemented |
HO0193 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $785 | $1,000 | Implemented |