Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
84
matching recommendationsSIC | 3085 | Plastics Bottles |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0205 # 04 Y:2000 | 04 | 2000 | INSULATE BARE EQUIPMENT | $4,536 | $4,508 | Implemented |
SF0205 # 05 Y:2000 | 05 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,404 | $9,230 | Implemented |
SF0205 # 06 Y:2000 | 06 | 2000 | INSTALL OCCUPANCY SENSORS | $1,007 | $1,080 | Implemented |
SF0205 # 07 Y:2000 | 07 | 2000 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $568 | $750 | Implemented |
SF0205 # 08 Y:2000 | 08 | 2000 | INSTALL OCCUPANCY SENSORS | $4,509 | $7,290 | Implemented |
SF0205 # 09 Y:2000 | 09 | 2000 | INSTALL SKYLIGHTS | $8,242 | $23,962 | Not Implemented |
SF0205 # 10 Y:2000 | 10 | 2000 | OPTIMIZE PLANT POWER FACTOR | $3,666 | $5,428 | Not Implemented |
SF0205 # 11 Y:2000 | 11 | 2000 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $48,746 | $120,000 | Not Implemented |
SF0173 # 01 Y:1999 | 01 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $358 | $451 | Not Implemented |
SF0173 # 02 Y:1999 | 02 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $269 | $506 | Not Implemented |
SF0173 # 03 Y:1999 | 03 | 1999 | INSTALL OCCUPANCY SENSORS | $423 | $1,200 | Not Implemented |
SF0173 # 04 Y:1999 | 04 | 1999 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,455 | $7,000 | Not Implemented |
SF0173 # 05 Y:1999 | 05 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $14,305 | $14,475 | Not Implemented |
SF0173 # 06 Y:1999 | 06 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $56,000 | $0 | Not Implemented |
SF0173 # 07 Y:1999 | 07 | 1999 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $3,500 | $164 | Not Implemented |
SF0173 # 08 Y:1999 | 08 | 1999 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $112,000 | $49,860 | Not Implemented |
SF0107 # 01 Y:1997 | 01 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $119 | $11,984 | Implemented |
SF0107 # 09 Y:1997 | 09 | 1997 | USE MORE EFFICIENT ADHESIVE APPLICATORS | $7,120 | $5,285 | Not Implemented |
SF0107 # 02 Y:1997 | 02 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,990 | $16,568 | Implemented |
SF0107 # 03 Y:1997 | 03 | 1997 | INSTALL OCCUPANCY SENSORS | $435 | $360 | Implemented |
SF0107 # 04 Y:1997 | 04 | 1997 | USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE | $1,601 | $7,400 | Implemented |
SF0107 # 05 Y:1997 | 05 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,713 | $0 | Implemented |
SF0107 # 06 Y:1997 | 06 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,365 | $3,180 | Not Implemented |
SF0107 # 07 Y:1997 | 07 | 1997 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,395 | $0 | Implemented |
SF0107 # 08 Y:1997 | 08 | 1997 | INSULATE BARE EQUIPMENT | $766 | $2,301 | Implemented |