IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

41

matching recommendations
Reset
SIC 3087 Custom Compound Purchased Resins
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
AM0832 # 04 Y:2022 04 2022 USE SYNTHETIC LUBRICANT $3,290 $500 Implemented
AM0832 # 03 Y:2022 03 2022 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $2,448 $0 Not Implemented
AM0832 # 02 Y:2022 02 2022 PAY UTILITY BILLS ON TIME $725 $0 Implemented
AM0832 # 01 Y:2022 01 2022 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES $234,880 $15,000 Implemented
AM0832 # 05 Y:2022 05 2022 MAINTAIN MACHINES TO REDUCE LEAKS $19,925 $50,000 Implemented
AM0547 # 05 Y:2008 05 2008 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $7,000 $0 Not Implemented
AM0547 # 01 Y:2008 01 2008 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $65,750 $20,000 Not Implemented
AM0547 # 02 Y:2008 02 2008 OPTIMIZE PLANT POWER FACTOR $27,000 $28,900 Not Implemented
AM0547 # 07 Y:2008 07 2008 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $3,150 $500 Not Implemented
AM0547 # 08 Y:2008 08 2008 INSTALL / REPAIR INSULATION ON STEAM LINES $170 $390 Not Implemented
AM0547 # 03 Y:2008 03 2008 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $15,020 $22,260 Not Implemented
AM0547 # 04 Y:2008 04 2008 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $14,600 $700 Not Implemented
AM0547 # 06 Y:2008 06 2008 USE SYNTHETIC LUBRICANT $4,300 $0 Not Implemented
AM0327 # 06 Y:1998 06 1998 ELIMINATE LEAKS IN WATER LINES AND VALVES $1,160 $210 Implemented
AM0327 # 07 Y:1998 07 1998 USE SYNTHETIC LUBRICANT $1,080 $0 Not Implemented
AM0327 # 05 Y:1998 05 1998 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,380 $0 Not Implemented
AM0327 # 04 Y:1998 04 1998 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,510 $2,070 Implemented
AM0327 # 03 Y:1998 03 1998 INSULATE BARE EQUIPMENT $4,260 $860 Implemented
AM0327 # 02 Y:1998 02 1998 $4,490 $0 Implemented
AM0327 # 01 Y:1998 01 1998 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,420 $0 Implemented
AM0327 # 08 Y:1998 08 1998 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $770 $1,700 Implemented
AM0327 # 09 Y:1998 09 1998 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $720 $250 Implemented
AM0272 # 06 Y:1996 06 1996 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS $1,350 $480 Implemented
AM0272 # 05 Y:1996 05 1996 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,650 $760 Implemented
AM0272 # 04 Y:1996 04 1996 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $1,840 $1,140 Implemented