Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,860
matching recommendationsSIC | 3089 | Plastics Products, Nec |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0105 # 05 Y:1987 | 05 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $3,875 | $1,100 | Implemented |
MA0105 # 07 Y:1987 | 07 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,580 | $6,238 | Implemented |
OK0234 # 01 Y:1987 | 01 | 1987 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,956 | $210 | Implemented |
OK0234 # 04 Y:1987 | 04 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $703 | $81 | Implemented |
OK0234 # 05 Y:1987 | 05 | 1987 | OPTIMIZE PLANT POWER FACTOR | $5,881 | $10,000 | Implemented |
OK0234 # 06 Y:1987 | 06 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $86 | $170 | Implemented |
OK0234 # 07 Y:1987 | 07 | 1987 | INSULATE BARE EQUIPMENT | $1,006 | $2,458 | Implemented |
CO0097 # 01 Y:1987 | 01 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $156 | $100 | Implemented |
CO0097 # 03 Y:1987 | 03 | 1987 | CENTRALIZE CONTROL OF EXHAUST FANS TO ENSURE THEIR SHUTDOWN, OR ESTABLISH PROGRAM TO ENSURE MANUAL SHUTDOWN | $2,950 | $65 | Implemented |
CO0097 # 06 Y:1987 | 06 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $3,327 | $3,200 | Implemented |
CO0097 # 07 Y:1987 | 07 | 1987 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $290 | $690 | Implemented |
CO0097 # 08 Y:1987 | 08 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,483 | $577 | Implemented |
AT0083 # 02 Y:1987 | 02 | 1987 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $293 | $500 | Implemented |
AT0083 # 05 Y:1987 | 05 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $889 | $1,656 | Implemented |
TN0314 # 01 Y:1987 | 01 | 1987 | INSTALL TIMERS AND/OR THERMOSTATS | $9,593 | $4,040 | Implemented |
TN0314 # 02 Y:1987 | 02 | 1987 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,581 | $16,250 | Implemented |
TN0314 # 06 Y:1987 | 06 | 1987 | INSULATE BARE EQUIPMENT | $1,839 | $1,160 | Implemented |
TN0314 # 07 Y:1987 | 07 | 1987 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,779 | $250 | Implemented |
LT0094 # 02 Y:1987 | 02 | 1987 | OPTIMIZE PLANT POWER FACTOR | $6,830 | $10,000 | Implemented |
LT0094 # 03 Y:1987 | 03 | 1987 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $950 | $755 | Implemented |
LT0094 # 04 Y:1987 | 04 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $684 | $97 | Implemented |
MA0096 # 01 Y:1987 | 01 | 1987 | INSULATE BARE EQUIPMENT | $1,581 | $551 | Implemented |
MA0096 # 02 Y:1987 | 02 | 1987 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $402 | $78 | Implemented |
MA0096 # 03 Y:1987 | 03 | 1987 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,922 | $746 | Implemented |
MA0096 # 07 Y:1987 | 07 | 1987 | USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS | $22,563 | $4,750 | Implemented |