IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

141

matching recommendations
Reset
SIC 32 Stone, Clay, And Glass Products
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0210 # 02 Y:2018 02 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $8,663 $2,000 Implemented
TT0210 # 03 Y:2018 03 2018 INSTALL OCCUPANCY SENSORS $1,508 $3,630 Implemented
TT0210 # 04 Y:2018 04 2018 INSTALL TIMERS AND/OR THERMOSTATS $716 $250 Implemented
TT0210 # 05 Y:2018 05 2018 APPLY FOR INVESTMENT INCENTIVES $579 $100 Implemented
AM0754 # 01 Y:2018 01 2018 INSTALL WASTE HEAT BOILER TO PROVIDE DIRECT POWER $63,539 $195,000 Implemented
AM0754 # 02 Y:2018 02 2018 OPTIMIZE PLANT POWER FACTOR $7,740 $11,520 Implemented
AM0754 # 03 Y:2018 03 2018 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,670 $1,000 Implemented
AM0754 # 04 Y:2018 04 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,555 $3,232 Implemented
AM0754 # 05 Y:2018 05 2018 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $1,270 $350 Not Implemented
AM0754 # 06 Y:2018 06 2018 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $560 $0 Not Implemented
AM0754 # 07 Y:2018 07 2018 USE SYNTHETIC LUBRICANT $312 $0 Implemented
AM0754 # 08 Y:2018 08 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $123 $9 Implemented
UU0134 # 01 Y:2018 01 2018 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $599,971 $264,049 Not Implemented
UU0134 # 02 Y:2018 02 2018 IMPROVE COMBUSTION CONTROL CAPABILITY $19,372 $15,000 Not Implemented
UU0134 # 03 Y:2018 03 2018 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $8,796 $22,888 Not Implemented
UU0134 # 04 Y:2018 04 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,606 $2,052 Not Implemented
UU0134 # 05 Y:2018 05 2018 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $1,549 $0 Implemented
UU0133 # 01 Y:2018 01 2018 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $473,255 $175,000 Not Implemented
UU0133 # 02 Y:2018 02 2018 USE POWER DURING OFF-PEAK PERIODS $206,416 $1,600 Not Implemented
UU0133 # 03 Y:2018 03 2018 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS $30,169 $97,680 Not Implemented
UU0133 # 04 Y:2018 04 2018 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $15,825 $0 Not Implemented
UU0133 # 05 Y:2018 05 2018 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,767 $5,679 Implemented
UU0133 # 06 Y:2018 06 2018 INSTALL OCCUPANCY SENSORS $2,849 $1,155 Implemented
SF0518 # 01 Y:2018 01 2018 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING $13,874 $3,023 Not Implemented
SF0518 # 02 Y:2018 02 2018 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $8,220 $4,857 Not Implemented