matching recommendationsSIC | 322 | Glass And Glassware, Pressed Or Blown |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0533 # 11 Y:1994 | 11 | 1994 | CONVERT TO AQUEOUS CLEANING SYSTEM | $3,325 | $3,000 | Implemented |
TN0533 # 08 Y:1994 | 08 | 1994 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $34,098 | $45,100 | Implemented |
TN0533 # 07 Y:1994 | 07 | 1994 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $56,576 | $32,240 | Implemented |
TN0533 # 06 Y:1994 | 06 | 1994 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,523 | $3,350 | Implemented |
TN0533 # 04 Y:1994 | 04 | 1994 | INSTALL TIMERS AND/OR THERMOSTATS | $1,318 | $700 | Implemented |
TN0533 # 02 Y:1994 | 02 | 1994 | INSULATE BARE EQUIPMENT | $4,449 | $200 | Implemented |
TN0496 # 02 Y:1993 | 02 | 1993 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $3,057 | $0 | Implemented |
TN0496 # 07 Y:1993 | 07 | 1993 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $603 | $0 | Implemented |
TN0496 # 05 Y:1993 | 05 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $1,353 | $4,000 | Implemented |
TN0496 # 04 Y:1993 | 04 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,000 | $820 | Implemented |
TN0496 # 03 Y:1993 | 03 | 1993 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,105 | $1,254 | Implemented |
TN0363 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $125,794 | $1,200 | Implemented |
TN0364 # 05 Y:1989 | 05 | 1989 | CLOSE OFF UNNEEDED STEAM LINES | $3,036 | $0 | Implemented |
TN0364 # 04 Y:1989 | 04 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,471 | $800 | Implemented |
TN0364 # 01 Y:1989 | 01 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $139,595 | $0 | Implemented |
TN0363 # 08 Y:1989 | 08 | 1989 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,085 | $600 | Implemented |
TN0363 # 07 Y:1989 | 07 | 1989 | INSTALL SET-BACK TIMERS | $2,215 | $0 | Implemented |
TN0363 # 06 Y:1989 | 06 | 1989 | KEEP LAMPS AND REFLECTORS CLEAN | $6,829 | $21,293 | Implemented |
TN0363 # 05 Y:1989 | 05 | 1989 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,789 | $7,480 | Implemented |
TN0363 # 04 Y:1989 | 04 | 1989 | USE MINIMUM STEAM OPERATING PRESSURE | $3,504 | $0 | Implemented |
TN0363 # 03 Y:1989 | 03 | 1989 | INSTALL STEAM TRAP | $8,302 | $3,450 | Implemented |
TN0363 # 02 Y:1989 | 02 | 1989 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $57,307 | $379,000 | Implemented |