Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
15
matching recommendationsSIC | 3241 | Cement, Hydraulic |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0216 # 01 Y:2001 | 01 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $83,016 | $0 | Implemented |
SF0216 # 02 Y:2001 | 02 | 2001 | UPGRADE CONTROLS ON COMPRESSORS | $24,891 | $400 | Implemented |
SF0216 # 03 Y:2001 | 03 | 2001 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $1,884 | $530 | Not Implemented |
SF0216 # 04 Y:2001 | 04 | 2001 | COOL COMPRESSOR AIR INTAKE WITH HEAT EXCHANGER | $14,286 | $2,150 | Implemented |
SF0216 # 05 Y:2001 | 05 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,905 | $7,982 | Implemented |
SF0216 # 06 Y:2001 | 06 | 2001 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $38,460 | $5,295 | Not Implemented |
SF0216 # 07 Y:2001 | 07 | 2001 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $30,349 | $44,387 | Not Implemented |
SF0216 # 08 Y:2001 | 08 | 2001 | INSTALL OCCUPANCY SENSORS | $828 | $1,691 | Not Implemented |
SF0216 # 09 Y:2001 | 09 | 2001 | REDUCE FLUID FLOW RATES | $1,160 | $5,108 | Not Implemented |
SF0216 # 10 Y:2001 | 10 | 2001 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $4,802,431 | $12,539,013 | Not Implemented |
AM0400 # 01 Y:2001 | 01 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $124,120 | $0 | Not Implemented |
AM0400 # 02 Y:2001 | 02 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,720 | $0 | Implemented |
AM0400 # 03 Y:2001 | 03 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,150 | $2,750 | Implemented |
AM0400 # 04 Y:2001 | 04 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $1,040 | $960 | Implemented |
AM0400 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $900 | $200 | Implemented |