Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
98
matching recommendationsSIC | 327 | Concrete, Gypsum, And Plaster Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0635 # 07 Y:2002 | 07 | 2002 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,070 | $200 | Implemented |
OK0635 # 06 Y:2002 | 06 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,624 | $2,468 | Implemented |
OK0635 # 05 Y:2002 | 05 | 2002 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $7,873 | $300 | Implemented |
OK0635 # 03 Y:2002 | 03 | 2002 | INSTALL / REPAIR INSULATION ON STEAM LINES | $9,648 | $6,750 | Not Implemented |
OK0635 # 02 Y:2002 | 02 | 2002 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,136 | $4,000 | Not Implemented |
OK0635 # 04 Y:2002 | 04 | 2002 | INSULATE BARE EQUIPMENT | $4,152 | $1,635 | Not Implemented |
OK0491 # 07 Y:1996 | 07 | 1996 | INSTALL / REPAIR INSULATION ON STEAM LINES | $109 | $62 | Implemented |
OK0491 # 06 Y:1996 | 06 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $234 | $400 | Implemented |
OK0491 # 05 Y:1996 | 05 | 1996 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $329 | $655 | Implemented |
OK0491 # 04 Y:1996 | 04 | 1996 | REPLACE GASOLINE WITH DIESEL, LPG, OR NATURAL GAS | $9,832 | $27,000 | Not Implemented |
OK0491 # 03 Y:1996 | 03 | 1996 | USE OPTIMUM THICKNESS INSULATION | $12,771 | $37,950 | Implemented |
OK0491 # 02 Y:1996 | 02 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,329 | $30 | Implemented |
OK0491 # 01 Y:1996 | 01 | 1996 | BURN WASTE OIL FOR HEAT | $1,349 | $2,995 | Not Implemented |
OK0432 # 02 Y:1994 | 02 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $6,476 | $0 | Not Implemented |
OK0432 # 03 Y:1994 | 03 | 1994 | USE PHOTOCELL CONTROLS | $1,649 | $120 | Implemented |
OK0432 # 01 Y:1994 | 01 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $9,384 | $30,309 | Implemented |
OK0432 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $321 | $170 | Not Implemented |
OK0428 # 05 Y:1994 | 05 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $705 | $2,530 | Not Implemented |
OK0428 # 04 Y:1994 | 04 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,456 | $0 | Not Implemented |
OK0428 # 03 Y:1994 | 03 | 1994 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $10,778 | $0 | Not Implemented |
OK0428 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,421 | $16,008 | Not Implemented |
OK0428 # 01 Y:1994 | 01 | 1994 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $1,053,065 | $5,000,000 | Not Implemented |
OK0348 # 02 Y:1991 | 02 | 1991 | INSTALL TIMERS AND/OR THERMOSTATS | $1,267 | $400 | Implemented |
OK0348 # 01 Y:1991 | 01 | 1991 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,500 | $0 | Implemented |
OK0348 # 03 Y:1991 | 03 | 1991 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $292 | $0 | Implemented |