Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
10,344
matching recommendationsSIC | 33 | Primary Metal Industries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0149 # 26 Y:1984 | 26 | 1984 | REPAIR AND ELIMINATE STEAM LEAKS | $276 | $300 | Implemented |
KU0149 # 27 Y:1984 | 27 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,258 | $906 | Not Implemented |
LT0014 # 01 Y:1984 | 01 | 1984 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $75,700 | $1,000 | Implemented |
LT0014 # 02 Y:1984 | 02 | 1984 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $2,320 | $332 | Implemented |
LT0014 # 03 Y:1984 | 03 | 1984 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $674 | $1,525 | Implemented |
LT0014 # 04 Y:1984 | 04 | 1984 | OPTIMIZE PLANT POWER FACTOR | $25,600 | $15,000 | Implemented |
LT0014 # 05 Y:1984 | 05 | 1984 | OPTIMIZE PLANT POWER FACTOR | $8,800 | $840 | Implemented |
UD0143 # 01 Y:1984 | 01 | 1984 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $8,182 | $0 | Implemented |
UD0143 # 02 Y:1984 | 02 | 1984 | INSULATE BARE EQUIPMENT | $2,369 | $2,500 | Implemented |
UD0143 # 03 Y:1984 | 03 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,542 | $387 | Implemented |
UD0143 # 04 Y:1984 | 04 | 1984 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $4,512 | $7,000 | Not Implemented |
MA0001 # 01 Y:1984 | 01 | 1984 | REPAIR OR REPLACE STEAM TRAPS | $1,657 | $30 | Implemented |
MA0001 # 02 Y:1984 | 02 | 1984 | KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE | $3,057 | $2,345 | Implemented |
MA0001 # 03 Y:1984 | 03 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $11,268 | $22,400 | Implemented |
LT0001 # 01 Y:1984 | 01 | 1984 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $6,220 | $12,200 | Implemented |
LT0001 # 02 Y:1984 | 02 | 1984 | ADJUST VENTS TO MINIMIZE ENERGY USE | $10,250 | $900 | Not Implemented |
LT0001 # 03 Y:1984 | 03 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,340 | $0 | Implemented |
LT0001 # 04 Y:1984 | 04 | 1984 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $1,420 | $0 | Not Implemented |
LT0001 # 05 Y:1984 | 05 | 1984 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $66,754 | $0 | Implemented |
OK0144 # 01 Y:1984 | 01 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,469 | $450 | Not Implemented |
OK0144 # 02 Y:1984 | 02 | 1984 | INSULATE BARE EQUIPMENT | $1,714 | $580 | Not Implemented |
OK0144 # 03 Y:1984 | 03 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $200 | $400 | Implemented |
OK0144 # 04 Y:1984 | 04 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $280 | $0 | Not Implemented |
OK0144 # 05 Y:1984 | 05 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $212 | $427 | Implemented |
OK0144 # 06 Y:1984 | 06 | 1984 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $93 | $0 | Implemented |