Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
20
matching recommendationsSIC | 3316 | Cold Finishing Of Steel Shapes |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0454 # 01 Y:2012 | 01 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,512 | $200 | Implemented |
SD0454 # 10 Y:2012 | 10 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,092 | $5,992 | Not Implemented |
SD0454 # 09 Y:2012 | 09 | 2012 | USE WASTE HEAT TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR | $148,802 | $420,000 | Not Implemented |
SD0454 # 08 Y:2012 | 08 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $14,363 | $31,050 | Not Implemented |
SD0454 # 07 Y:2012 | 07 | 2012 | USE WASTE HEAT STEAM FOR ABSORPTION REFRIGERATION | $28,169 | $55,000 | Not Implemented |
SD0454 # 06 Y:2012 | 06 | 2012 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,826 | $6,000 | Not Implemented |
SD0454 # 05 Y:2012 | 05 | 2012 | INSULATE BARE EQUIPMENT | $14,303 | $13,546 | Implemented |
SD0454 # 04 Y:2012 | 04 | 2012 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $5,354 | $2,350 | Not Implemented |
SD0454 # 03 Y:2012 | 03 | 2012 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $6,156 | $2,000 | Not Implemented |
SD0454 # 02 Y:2012 | 02 | 2012 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,236 | $2,700 | Implemented |
LE0332 # 01 Y:2012 | 01 | 2012 | USE SOLAR HEAT TO MAKE ELECTRICTY | $66,813 | $0 | Not Implemented |
LE0332 # 10 Y:2012 | 10 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $706 | $4,580 | Not Implemented |
LE0332 # 09 Y:2012 | 09 | 2012 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,360 | $6,400 | Not Implemented |
LE0332 # 08 Y:2012 | 08 | 2012 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,829 | $40 | Implemented |
LE0332 # 07 Y:2012 | 07 | 2012 | DEVELOP STANDARD OPERATING PROCEDURES | $6,689 | $0 | Implemented |
LE0332 # 06 Y:2012 | 06 | 2012 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $7,328 | $23,400 | Not Implemented |
LE0332 # 05 Y:2012 | 05 | 2012 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $8,856 | $28,000 | Not Implemented |
LE0332 # 04 Y:2012 | 04 | 2012 | INSTALL OCCUPANCY SENSORS | $9,659 | $24,370 | Not Implemented |
LE0332 # 03 Y:2012 | 03 | 2012 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $12,677 | $25,375 | Not Implemented |
LE0332 # 02 Y:2012 | 02 | 2012 | MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE | $16,976 | $7,660 | Not Implemented |