Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
897
matching recommendationsSIC | 332 | Iron And Steel Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
ND0202 # 07 Y:1994 | 07 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $960 | $1,470 | Implemented |
AM0221 # 03 Y:1994 | 03 | 1994 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $5,430 | $0 | Implemented |
AM0221 # 04 Y:1994 | 04 | 1994 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $3,180 | $200 | Implemented |
AM0221 # 05 Y:1994 | 05 | 1994 | RECYCLE CASTING SAND | $37,570 | $0 | Implemented |
IA0091 # 01 Y:1994 | 01 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $64,093 | $4,700 | Implemented |
IA0091 # 02 Y:1994 | 02 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,691 | $9,871 | Implemented |
IA0091 # 04 Y:1994 | 04 | 1994 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,200 | $150 | Implemented |
IA0091 # 05 Y:1994 | 05 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,028 | $40 | Implemented |
IA0091 # 06 Y:1994 | 06 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,181 | $1,168 | Implemented |
KU0436 # 01 Y:1994 | 01 | 1994 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $20,016 | $3,500 | Implemented |
KU0436 # 02 Y:1994 | 02 | 1994 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $5,311 | $11,979 | Implemented |
KU0436 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,628 | $3,559 | Implemented |
KU0436 # 06 Y:1994 | 06 | 1994 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,442 | $155 | Implemented |
KU0436 # 07 Y:1994 | 07 | 1994 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,335 | $326 | Implemented |
KU0436 # 09 Y:1994 | 09 | 1994 | USE SYNTHETIC LUBRICANT | $670 | $510 | Implemented |
TN0529 # 01 Y:1994 | 01 | 1994 | COVER OPEN TANKS | $8,253 | $100 | Implemented |
TN0529 # 02 Y:1994 | 02 | 1994 | RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR | $3,332 | $0 | Implemented |
TN0529 # 07 Y:1994 | 07 | 1994 | INSTALL SHROUDING ON MACHINES TO PREVENT SPLASHING | $7,800 | $344 | Implemented |
TN0529 # 09 Y:1994 | 09 | 1994 | IMPROVED MATERIAL HANDLING (MIXING AND TRANSFER) | $5,574 | $0 | Implemented |
ND0147 # 01 Y:1993 | 01 | 1993 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $20,977 | $2,160 | Implemented |
ND0147 # 03 Y:1993 | 03 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,829 | $300 | Implemented |
UD0422 # 01 Y:1994 | 01 | 1994 | OPTIMIZE PLANT POWER FACTOR | $2,520 | $8,000 | Implemented |
UD0422 # 02 Y:1994 | 02 | 1994 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $20,950 | $5,000 | Implemented |
UD0422 # 03 Y:1994 | 03 | 1994 | CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS | $1,812 | $6,000 | Implemented |
UD0422 # 04 Y:1994 | 04 | 1994 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $691 | $3,827 | Implemented |