Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,106
matching recommendationsSIC | 3321 | Gray And Ductile Iron Foundries |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TS0015 # 02 Y:1985 | 02 | 1985 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $951 | $575 | Implemented |
TS0015 # 03 Y:1985 | 03 | 1985 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $433 | $150 | Implemented |
TS0015 # 04 Y:1985 | 04 | 1985 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $376 | $0 | Implemented |
TS0015 # 05 Y:1985 | 05 | 1985 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $3,190 | $2,100 | Implemented |
OK0139 # 03 Y:1984 | 03 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $429 | $130 | Not Implemented |
OK0139 # 04 Y:1984 | 04 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $626 | $135 | Not Implemented |
OK0139 # 05 Y:1984 | 05 | 1984 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $222 | $0 | Not Implemented |
OK0139 # 06 Y:1984 | 06 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $52 | $180 | Not Implemented |
UD0119 # 01 Y:1984 | 01 | 1984 | REVISE SMOKE CLEANUP FROM OPERATIONS | $5,989 | $1,000 | Implemented |
UD0119 # 02 Y:1984 | 02 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,135 | $700 | Implemented |
UD0119 # 03 Y:1984 | 03 | 1984 | REDESIGN PROCESS | $683 | $2,000 | Implemented |
UD0119 # 04 Y:1984 | 04 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $162 | $700 | Implemented |
OK0139 # 01 Y:1984 | 01 | 1984 | INSTALL TIMERS AND/OR THERMOSTATS | $90 | $325 | Not Implemented |
OK0139 # 02 Y:1984 | 02 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $519 | $115 | Not Implemented |
OK0093 # 01 Y:1983 | 01 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $470 | $824 | Not Implemented |
OK0093 # 02 Y:1983 | 02 | 1983 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $752 | $2,405 | Not Implemented |
OK0093 # 03 Y:1983 | 03 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $233 | $103 | Not Implemented |
UD0088 # 01 Y:1983 | 01 | 1983 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $4,182 | $0 | Implemented |
UD0088 # 02 Y:1983 | 02 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,951 | $9,396 | Implemented |
OK0079 # 01 Y:1983 | 01 | 1983 | INSTALL TIMERS AND/OR THERMOSTATS | $2,195 | $560 | Not Implemented |
OK0079 # 02 Y:1983 | 02 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $922 | $956 | Not Implemented |
OK0079 # 03 Y:1983 | 03 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $966 | $450 | Not Implemented |
OK0079 # 04 Y:1983 | 04 | 1983 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $282 | $505 | Not Implemented |
OK0079 # 05 Y:1983 | 05 | 1983 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $322 | $450 | Not Implemented |
TN0164 # 01 Y:1983 | 01 | 1983 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,300 | $5,000 | Not Implemented |