Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
42
matching recommendationsSIC | 3334 | Primary Aluminum |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0565 # 02 Y:2023 | 02 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $139,376 | $1,265,613 | Implemented |
AS0565 # 01 Y:2023 | 01 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $583,260 | $500 | Implemented |
AS0565 # 07 Y:2023 | 07 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $454 | $720 | Implemented |
AS0565 # 05 Y:2023 | 05 | 2023 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $1,336 | $75 | Implemented |
GT0936 # 01 Y:2019 | 01 | 2019 | INSTALL OCCUPANCY SENSORS | $24,628 | $2,456 | Implemented |
GT0936 # 02 Y:2019 | 02 | 2019 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $17,484 | $2,000 | Implemented |
GT0936 # 03 Y:2019 | 03 | 2019 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $16,073 | $3,500 | Implemented |
GT0936 # 04 Y:2019 | 04 | 2019 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $35,634 | $19,362 | Implemented |
GT0936 # 07 Y:2019 | 07 | 2019 | BURN A LESS EXPENSIVE GRADE OF FUEL | $9,120 | $9,016 | Implemented |
UA0159 # 06 Y:2016 | 06 | 2016 | TURN OFF EQUIPMENT WHEN NOT IN USE | $82,252 | $55 | Implemented |
UA0159 # 04 Y:2016 | 04 | 2016 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,382 | $2,400 | Implemented |
MZ0187 # 02 Y:2015 | 02 | 2015 | USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS | $9,635 | $6,500 | Implemented |
MZ0187 # 05 Y:2015 | 05 | 2015 | REPAIR AND ELIMINATE STEAM LEAKS | $3,321 | $1,440 | Implemented |
MZ0187 # 03 Y:2015 | 03 | 2015 | REPAIR FURNACES AND OVEN DOORS SO THAT THEY SEAL EFFICIENTLY | $684 | $380 | Implemented |
MZ0187 # 04 Y:2015 | 04 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,096 | $5,600 | Implemented |
UM0417 # 05 Y:2012 | 05 | 2012 | UPGRADE CONTROLS ON COMPRESSORS | $6,000 | $200 | Implemented |
UM0417 # 01 Y:2012 | 01 | 2012 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,780 | $58,125 | Implemented |
MZ0071 # 02 Y:2011 | 02 | 2011 | INSTALL OCCUPANCY SENSORS | $285 | $610 | Implemented |
MZ0071 # 03 Y:2011 | 03 | 2011 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $429 | $0 | Implemented |
MZ0071 # 04 Y:2011 | 04 | 2011 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $19,137 | $1,000 | Implemented |
MZ0071 # 05 Y:2011 | 05 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,810 | $1,300 | Implemented |
MZ0071 # 07 Y:2011 | 07 | 2011 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,223 | $800 | Implemented |
MZ0071 # 08 Y:2011 | 08 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $35 | $50 | Implemented |
MZ0071 # 10 Y:2011 | 10 | 2011 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $3,736 | $6,494 | Implemented |
MZ0071 # 09 Y:2011 | 09 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,831 | $0 | Implemented |