Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
16
matching recommendationsSIC | 3341 | Secondary Nonferrous Metals |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0151 # 01 Y:1996 | 01 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,415 | $4,860 | Implemented |
SD0151 # 02 Y:1996 | 02 | 1996 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $9,302 | $13,500 | Not Implemented |
SD0151 # 03 Y:1996 | 03 | 1996 | INSTALL TIMERS AND/OR THERMOSTATS | $795 | $600 | Not Implemented |
SD0151 # 04 Y:1996 | 04 | 1996 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,233 | $440 | Implemented |
SD0151 # 05 Y:1996 | 05 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,509 | $3,663 | Implemented |
SD0151 # 06 Y:1996 | 06 | 1996 | INSTALL SPECTRAL REFLECTORS / DELAMP | $4,479 | $5,640 | Implemented |
SD0151 # 07 Y:1996 | 07 | 1996 | INSTALL OCCUPANCY SENSORS | $426 | $369 | Implemented |
SD0151 # 08 Y:1996 | 08 | 1996 | USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES | $2,885 | $1,450 | Implemented |
SD0151 # 09 Y:1996 | 09 | 1996 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $91 | $200 | Implemented |
OR0262 # 01 Y:1996 | 01 | 1996 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $35,059 | $1,690 | Not Implemented |
OR0262 # 02 Y:1996 | 02 | 1996 | FILTER AND REUSE HYDRAULIC OIL | $53,160 | $3,850 | Not Implemented |
OR0262 # 03 Y:1996 | 03 | 1996 | REDUCE SCRAP PRODUCTION | $130,236 | $29,640 | Not Implemented |
OR0262 # 04 Y:1996 | 04 | 1996 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $28,400 | $8,250 | Not Implemented |
OR0262 # 05 Y:1996 | 05 | 1996 | OPTIMIZE PLANT POWER FACTOR | $3,101 | $6,600 | Not Implemented |
OR0262 # 06 Y:1996 | 06 | 1996 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,084 | $10,701 | Not Implemented |
OR0262 # 07 Y:1996 | 07 | 1996 | UPGRADE CONTROLS ON COMPRESSORS | $6,882 | $27,454 | Not Implemented |