Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
17
matching recommendationsSIC | 3351 | Copper Rolling And Drawing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IP0184 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,142 | $12,019 | Implemented |
IP0184 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $31,216 | $17,960 | Implemented |
IP0184 # 03 Y:2023 | 03 | 2023 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $8,667 | $2,615 | Implemented |
IP0184 # 02 Y:2023 | 02 | 2023 | USE MINIMUM STEAM OPERATING PRESSURE | $83,429 | $20,365 | Implemented |
IP0184 # 01 Y:2023 | 01 | 2023 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $14,493 | $0 | Implemented |
IP0136 # 04 Y:2020 | 04 | 2020 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,455 | $69 | Implemented |
IP0136 # 07 Y:2020 | 07 | 2020 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,172 | $8,600 | Implemented |
IP0136 # 06 Y:2020 | 06 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $27,563 | $32,451 | Implemented |
IP0136 # 05 Y:2020 | 05 | 2020 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $12,685 | $10,860 | Implemented |
IP0136 # 02 Y:2020 | 02 | 2020 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $921 | $0 | Implemented |
IP0136 # 01 Y:2020 | 01 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $672 | $0 | Implemented |
IP0074 # 02 Y:2016 | 02 | 2016 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $11,888 | $292 | Implemented |
IP0074 # 09 Y:2016 | 09 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $29,616 | $56,725 | Implemented |
IP0074 # 08 Y:2016 | 08 | 2016 | APPLY FOR INVESTMENT INCENTIVES | $6,707 | $5,000 | Implemented |
IP0074 # 06 Y:2016 | 06 | 2016 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $473 | $101 | Implemented |
IP0074 # 05 Y:2016 | 05 | 2016 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,366 | $308 | Implemented |
IP0074 # 04 Y:2016 | 04 | 2016 | LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA | $13,398 | $951 | Implemented |