Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
768
matching recommendationsSIC | 3354 | Aluminum Extruded Products |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0383 # 09 Y:2004 | 09 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $406 | $367 | Not Implemented |
AS0383 # 10 Y:2004 | 10 | 2004 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $577,735 | $9,735 | Not Implemented |
UF0323 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,288 | $23,205 | Implemented |
UF0323 # 02 Y:2003 | 02 | 2003 | ADD AREA LIGHTING SWITCHES | $2,366 | $4,075 | Not Implemented |
UF0323 # 03 Y:2003 | 03 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $12,002 | $0 | Not Implemented |
UF0323 # 04 Y:2003 | 04 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $26,966 | $104,168 | Implemented |
UF0323 # 05 Y:2003 | 05 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $14,475 | $370 | Implemented |
UF0323 # 06 Y:2003 | 06 | 2003 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $76,790 | $65 | Implemented |
UF0323 # 07 Y:2003 | 07 | 2003 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $4,852 | $618 | Not Implemented |
UF0323 # 08 Y:2003 | 08 | 2003 | INSTALL OCCUPANCY SENSORS | $1,385 | $831 | Not Implemented |
UF0323 # 09 Y:2003 | 09 | 2003 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $774 | $3,496 | Not Implemented |
UF0323 # 10 Y:2003 | 10 | 2003 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $69,343 | $420,000 | Implemented |
UU0042 # 01 Y:2003 | 01 | 2003 | OPTIMIZE PLANT POWER FACTOR | $15,620 | $8,000 | Not Implemented |
UU0042 # 02 Y:2003 | 02 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,027 | $1,500 | Not Implemented |
UU0042 # 03 Y:2003 | 03 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $632 | $550 | Not Implemented |
UU0042 # 04 Y:2003 | 04 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $9,960 | $0 | Not Implemented |
UU0042 # 05 Y:2003 | 05 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $2,836 | $20,051 | Not Implemented |
UU0042 # 06 Y:2003 | 06 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $420 | $406 | Not Implemented |
UU0042 # 07 Y:2003 | 07 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $792 | $2,296 | Not Implemented |
UU0042 # 08 Y:2003 | 08 | 2003 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $14,607 | $100,240 | Not Implemented |
UM0227 # 01 Y:2003 | 01 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,930 | $1,000 | Not Implemented |
UM0227 # 02 Y:2003 | 02 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,000 | $1,725 | Implemented |
UM0227 # 03 Y:2003 | 03 | 2003 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $5,893 | $10,000 | Not Implemented |
UM0227 # 04 Y:2003 | 04 | 2003 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,016 | $1,920 | Not Implemented |
UM0227 # 05 Y:2003 | 05 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,702 | $19,995 | Not Implemented |